188 SECTION 30<br />

SECTION 30<br />

PAYMENTS TO CONTRACTORS<br />

30.1 Requirement of clause 7<br />

(1) Clause 7 of the conditions of contract in Forms no. CPWD 7, 8 & 9 provides that no payment shall<br />

be made for works or supplies estimated to cost less than Rs. 50,000 till after the whole of the<br />

work or supply shall have been completed and a certificate of completion given. In the case of<br />

works or supplies estimated to cost more than Rs.50,000, the contractor shall, on submitting the<br />

bill thereof, be entitled to receive a monthly payment as passed by the Engineer-in-charge. Para<br />

7.12 of this Manual may be seen for submission of computerized bills by the contractor.<br />

(2) On account payments are also permissible under the conditions of contract in Forms no. CPWD 12,<br />

piece work agreement in Form no. CPWD 10 and work order Form no. CPWD 11-A. The contractors<br />

should be required by the Engineer-in-charge to submit their bills by a fixed date in accordance with<br />

the terms of the contract, e.g. clause 7 of Forms no. CPWD 7 and 8. The Assistant Engineer should<br />

supply to the contractor a copy of the measurements and a statement of part rates to be paid, at least<br />

3 clear days in advance of such date fixed by the Executive Engineer. The payment to the contractor<br />

shall be made only on submission of the bill by him.<br />

30.1.A - Stage Payments for Running & Final Bill (Added vide OM/MAN/233)<br />

Initially the system of stage payments may be implemented in each zone for suitable projects/<br />

works as a test case. This system is suitable for works of repetitive nature. Under clause 7 of<br />

CPWD 7/8, GCC 2010 Running Account and Final payments to be made after completion of a<br />

particular stage needs to be defined keeping in view the following guidelines:-<br />

(i) Payment for foundation work can also be defined in stages if all the foundations of one<br />

block/segment considered for each stage are of similar design. If not the payment for<br />

foundation works to be made as per actual measurements.<br />

(ii) System of stage payments may be followed for residential and non-residential buildings<br />

where floor plans are identical.<br />

(iii) Each stage should be well defined. Floor levels or any other level such as Lintel level/Sill<br />

level of each block/each segment may be the basis to allow stage payment.<br />

(iv) The measurements of one complete unit for each defined stage shall be recorded and test<br />

checked by JE/AE/EE. Hidden measurements shall be test checked 100% by JE/AE & at<br />

least 10% of the hidden measurements are to be test checked by EE.<br />

(v) After completion of each stage a certificate will be recorded by JE & AE that work has<br />

been executed strictly as per the measurements of standard unit as recorded earlier.<br />

Completion of each stage is also to be certified by EE. For outer stations test check of EE<br />

may be exercised in alternate running account bills.<br />

(vi) Payment Schedule defining each stage of payment subject to minimum amount of Running<br />

Account Bill is to be mentioned under clause 7 of Schedule F of CPWD-7/8<br />

(vii) No part payment shall be allowed for incomplete stage.<br />

30.1.1 Register of Bills and its review<br />

(1) The Divisional Officer should maintain a register to keep a record of the monthly running<br />

payments made to the contractors in respect of contracts costing above Rs.50,000 in the<br />

proforma prescribed in Appendix 12. As and when a bill is submitted, the same shall be entered<br />

in this register.<br />

(2) The register should be reviewed by the Executive Engineer regularly to ensure that payments<br />

are being made to the contractors in time.<br />

(3) The register should be posted at the time of making monthly running payment to the contractor.