24.10.2012 Views

CONTENTS - Central Public Works Department

CONTENTS - Central Public Works Department

CONTENTS - Central Public Works Department

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

184 SECTION 29<br />

SECTION 29<br />

EXTENSION OF TIME AND COMPENSATION FOR DELAY<br />

29.1 General Principles<br />

(1) At the time of issuing Notice Inviting Tenders for a particular work, the Engineer-in-charge should<br />

specify the time allowed for completion of the work consistent with the magnitude and urgency of<br />

the work.<br />

(2) The time allowed for carrying out the work as entered in the contract shall be strictly observed by<br />

the contractor, and shall be reckoned from the .....th day (as mentioned in the NIT) after the date<br />

on which the letter of acceptance is given to the contractor.<br />

(3) The work shall be proceeded with all due diligence on the part of the contractor throughout the<br />

stipulated period of the contract (time being deemed to be the essence of the contract).<br />

(4) To ensure good progress of the work during execution, the contractor shall be bound, in all cases,<br />

in which the time allowed for any work exceeds one month (save for special job), to complete the<br />

work as per the milestones given in Schedule ‘F’ given under clause 5 of the contract, or as per the<br />

re-scheduled milestones. However, for special jobs, if a time schedule has been submitted by the<br />

contractor and the same has been accepted by the Engineer-in-charge, the contractor shall comply<br />

with such time schedule. (Provisions under para 33.5 of this Manual may also be seen).<br />

29.1.1 Review of progress of the work<br />

(1) The NIT approving authority shall stipulate time schedule for physical milestones in Schedule ‘F’<br />

under clause 5 of the General Conditions of Contract, in the NIT. The tender accepting authority<br />

shall review the progress of work each month with all the concerned disciplines including the<br />

contractor. The factors affecting the progress shall be identified and discussed and remedial<br />

measures taken, wherever required. Detailed minutes of these meetings shall be issued. Whenever<br />

physical milestones have been specified in the NIT, the detailed review may be carried out on the<br />

dates specified for such milestones.<br />

(2) If an extension of time has been granted by the competent authority for genuine hindrances, he<br />

should re-schedule the milestones appropriately for the work.<br />

29.2 Requirements of clause 5<br />

Clause 5 of CPWD Forms no. 7 and 8 and Clause 4 of CPWD Form no. 9 empower the Engineer-incharge<br />

to grant extension of time for the completion of the work on certain conditions. He can exercise<br />

such powers if the following conditions are satisfied:<br />

(i) The contractor must apply to the Engineer-in-charge in writing for extension of time.<br />

(ii) Such an application must state the grounds that hindered the contractor in the execution of the<br />

work within the stipulated time.<br />

(iii) Such an application must be made within 14 days of the date on which such hindrance arose.<br />

(iv) The Engineer-in-charge must be of the opinion that the grounds shown for the extension of time<br />

are reasonable.<br />

29.3 Powers of officers for grant of extension of time<br />

The powers for grant of extension of time have been delegated to CPWD Officers as shown in Appendix-1.<br />

29.4 Grant of extension of time without application<br />

(1) Based on the Hindrance Register where adequate and proper grounds exist, the Engineer-incharge<br />

can grant extension of time even in the absence of application from the contractor under<br />

Clause 5.<br />

(2) The extension, in order to be binding, will have to be by the ‘agreement’ of the parties, express or<br />

implied. It, therefore, follows that if the extension of time is granted by the Executive Engineer and

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!