176 SECTION 26<br />

particular date, receipt during the day, issue during the day and closing balance at the end<br />

of the day (The entries for receipts and issues shall be updated immediately on physical<br />

receipt and physical issue, and also at the end of the day).<br />

(b) Procedure for indenting, receipt and issue of cement and steel<br />

While issuing an indent for fresh cement/steel, the balance material available at the site<br />

should be checked. The Assistant Engineer must record on the body of the indent, the<br />

balance of such material available at the time and date of issue of the indent, which should<br />

be taken into account by the Executive Engineer before signing the indent.<br />

At the time of receipt of the materials, not only the date but also the time of receipt shall be<br />

mentioned in the Cement Register as well as in the MAS Register. The entries should be<br />

made separately for each truck, giving the gate pass number. The consignee should also<br />

indicate the time/date of receipt of material on the gate pass that is returned to the <strong>Central</strong><br />

Stores through the transporter. Gate pass should be counter signed by the Assistant<br />

Engineer for all quantities of cement received against indents of 10 tonnes and above.<br />

The cement/steel and other materials received from Stores/Local purchase etc. on any<br />

particular day, shall not be used in the work or transferred to any other work for 26 hours<br />

from the time of receipt at site, for physical check and verification by the Assistant Engineer.<br />

The cement already available in the store should be consumed first, before issue from the<br />

new consignment. Similarly, new steel items should be stacked in countable shape to<br />

facilitate physical check before these are used. The principle of first in and first out in<br />

issuing cement bags should be strictly followed.<br />

(c) Checking of steel consumption<br />

For making comparison of the actual consumption of steel with the theoretical consumption,<br />

each diameter of steel bars should be treated as an individual item issued departmentally<br />

and check on theoretical consumption should be applied to each diameter.<br />

Theoretical consumption statement for steel bars should be prepared along with every<br />

running bill. Should there be any case of issue being less or just equal in any particular<br />

diameter/section than the actual consumption, this should be properly investigated. If such<br />

issue, diameter wise/section wise or in total, is very much higher than the consumption, it<br />

should be generally ensured that the balance steel is available at site in good condition and<br />

this should be certified by the Assistant Engineer. Any serious discrepancies that are<br />

noticed should be reported to the Superintending Engineer.<br />

(3) Similar precautions should be taken in the case of all other materials issued by the <strong>Department</strong>.<br />

(4) Recovery from the contractor<br />

The recovery from the contractor shall be regulated as per clause 42 of the agreement, and its<br />

interpretation may also be referred to under section 33 of this Manual.<br />

26.4 Issue rates and recovery of cost<br />

(1) Issue rates of cement, steel or any other items in the contract should not be less than the market<br />

rates of these commodities irrespective of the issue rates of the <strong>Central</strong> Stores.<br />

(2) Recovery for materials issued<br />

The recovery from a contractor on account of the cost of materials issued to him for use on a work<br />

should ordinarily be made by deduction from the first bill authorizing an advance payment, or an on<br />

account payment to him for the work. However, the recovery from the contractor on account of the<br />

cost of materials issued to him for use on a work may be made gradually by the Divisional Officer<br />

on the basis of the theoretical consumption plus wastage of the material used in the work as<br />

measured up-to-date. For each bill, the field staff should certify that the balance material(s) is(are)<br />

available in the contractor’s custody. In case of shortage, the cost of the same should be immediately<br />

recovered from the contractor.