SECTION 24<br />

SECTION 24<br />

EXTRA SUBSTITUTED AND DEVIATED ITEMS OF WORK<br />

24.1 Deviations<br />

Deviation means deviation in quantities of items, i.e. where there is increase or decrease in the quantities<br />

of items of work in the agreement.<br />

24.1.1 Market rates for quantities deviating beyond certain limit<br />

As per provisions of clause 12.2 of GCC, in case of agreement items, substituted item, agreement<br />

cum substituted items which exceed the limit stipulated in schedule F, of the contract, the contractor<br />

within 15 days of receipt of order or occurance of the excess, can claim revision of rates, supported by<br />

proper analysis, for excess quantities. Engineer-in-Charge shall consider the analysis submitted by<br />

contractor and determine the rates on basis of market rates.<br />

Further as per provision of clause 12.3 of GCC, in case market rates are less than the agreement rates<br />

then in such a case Engineer-in-Charge should give notice to the contractor within one month of occurance<br />

of the excess and should decide the rates based on market rates considering the reply of contractor.<br />

The rates should be worked out by adopting the market rates of material/labour, prevailing at the time<br />

of occurance of excess, in the relevant item as adopted in the justification<br />

24.1.2 Sanction of deviations<br />

Apart from obligation of sanctioning rates under clause 12.2, 12.3 of contract, a proper check is<br />

needed on deviations in quantities on higher/lower side for each and every item. In order to exercise<br />

proper check on deviations, following procedures shall be followed.<br />

(1) Deviations in quantities of individual item up to + 10% of agreement quantities will not need any<br />

prior approval of technical sanction authority and sanction of deviations is not required.<br />

(2) Deviation in quantities of individual item beyond the limit of + 10% but within deviation limit as<br />

specified under clause 12 of the contract, will not require prior approval of technical sanction<br />

authority but total deviation (including initial + 10% ) shall be sanctioned by officers as per delegation<br />

of powers. (Modified as per OM/MAN/175)<br />

(3) If total deviation of quantity of individual item is beyond the deviation limit as specified under clause<br />

12 of the contract then deviations beyond the limit of + 10% should not be made at site without in<br />

principle approval of technical sanction authority. Once in principle approval is obtained, the total<br />

deviations (including + 10%) shall be sanctioned by the officers as per delegation of powers.<br />

(Added as per OM/MAN/175)<br />

(4) In case of deviations occurring in the quantities of substituted/extra items/ deviation in quantity of<br />

any item already sanctioned, then revised sanction should be taken from the competent authority.<br />

(5) Total deviation in quantity of an item shall be sanctioned by one authority only whosoever is<br />

competent to sanction total deviation of the item.<br />

(6) Minus deviation is to be sanctioned on the basis of agreement rate irrespective of deviation limit.<br />

(Added as per OM/MAN/215)<br />

The amount of a deviation statement shall be the sum of absolute value of deviated amounts<br />

of all individual items. (Modified as per OM/MAN/153)<br />

24.2 Extra/Substituted Items<br />

24.2.1 Definition<br />

(1) Extra items of work are items that are completely new, and are in addition to the items contained in<br />

the contract.<br />