160 SECTION 22<br />

SECTION 22<br />

REFUND OF SECURITY DEPOSIT AND PERFORMANCE GUARANTEE<br />

22.1 Conditions for refund of security deposit and performance guarantee<br />

The security deposit and performance guarantee shall not be refunded to a contractor except in<br />

accordance with the terms of his security bond or agreement.<br />

22.1.1 Recording of completion certificate<br />

In case the completion certificate is recorded by a Junior Engineer/Sectional Officer, the Sub-Divisional<br />

Officer concerned shall countersign it within one month. In case of works costing more than the normal<br />

acceptance power of tender of the Executive Engineer, the original certificate must be recorded by the<br />

Sub-Divisional Officer and countersigned by the Executive Engineer within one month. If the Sub-Divisional<br />

Officer is not available the Executive Engineer should himself record the certificate.<br />

22.1.2 Refund of performance guarantee<br />

The performance guarantee shall be refunded to the contractor soon after the completion of the work<br />

and recording of the completion certificate as above.<br />

22.1.3 Refund of security deposit<br />

(1) In the case of works executed against agreements in Forms CPWD 7 & 8 the refund of security<br />

deposit to a contractor on the completion of works is regulated by Clause 17 thereof. This clause<br />

envisages the issue of a completion certificate in terms of Clause 8 of the Contract. Such completion<br />

certificate shall be issued by the authority in a manner detailed under section 30.<br />

(2) The period of maintenance as prescribed in Clause 17 of the Contract will be counted from the<br />

date of completion as recorded in the certificate mentioned above. The security deposit of the<br />

contractor should be refunded by the Executive Engineer after the prescribed maintenance period<br />

as stipulated in the agreement or after the date in which the final bill has been prepared and<br />

passed for payment, which ever is later.<br />

(3) The Divisional Officers should keep a close watch on the delays in the refund of security deposit<br />

to the contractors, and for this purpose they should periodically review the Register of Security<br />

Deposit Form CPWA 67 maintained in the Division. (The instructions contained in para 23.4.20 of<br />

the CPWA Code shall continue to be observed as a normal procedure).<br />

22.2 Refund of security deposit in cases of delay in final bill<br />

(1) Where there is a delay in payment of final bill, the Superintending Engineer shall make an<br />

assessment of the likely recoveries against the contractor, and order release of as much security<br />

deposit as possible unless he has reasons to withhold the release of security deposit to the<br />

contractor. These reasons should be recorded by him in writing.<br />

(2) The Superintending Engineer shall satisfy himself that the following formalities are completed by<br />

all concerned before exercising his discretionary power for part payment of security deposits:<br />

(i) Formalities to be completed by the departmental officers<br />

(a) Completion of prescribed test checks of measurements by Executive Engineer/Assistant<br />

Engineer.<br />

(b) Sanction of extra/substituted items by the competent authorities.<br />

(c) Decision on levy of compensation, etc.<br />

(ii) Formalities to be completed by contractor<br />

(a) Acceptance of final measurement recorded by the departmental officers.<br />

(b) Applying for extension of time as and when required immediately.<br />

(c) Rectification of defects pointed out by the departmental officers.<br />

(d) Completion of work in all respects, including clearance of site, etc.<br />

(e) return of surplus materials issued by the department immediately on completion of work or<br />

as and when it comes to light.