Table - 3 : Salient features of the recommended structures<br />
No Type of Structure/Practice Total Structures Total Cost Estimated Storage<br />
(in Lac. Rupees) (in mcm)<br />
1 Boulder Check Dam cum 04 15.24 0.06<br />
2 Masonry Stop Dam 02 68.13 0.06<br />
3. Sub Surface Dykes 04 12.18 0.048<br />
4. Desiltation of Tanks 04 0.78 0.002<br />
5. Roof Top Structures 01 0.18 —<br />
6. Percolation Tank 01 0.015<br />
7 Silt Traps 02 —<br />
Total 18 104.02 0.185<br />
Thus, in all 07 different types of structures have been suggested and the estimated cost of these structures<br />
in Rs.1.05 Crore The cost will ensure an additional surface storage of 0.185 mcm, over and above recharge<br />
through existing tank (1.06 mcm) will be added. Thus total water availability will be 1.24 mcm.<br />
Map-3 : Final Structure Map of Naini Watershed<br />