AGENDA 3.1.2 - Board of Engineers Malaysia
AGENDA 3.1.2 - Board of Engineers Malaysia
AGENDA 3.1.2 - Board of Engineers Malaysia
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
RECOMMENDATION<br />
BY THE INVESTIGATING COMMITTEE TO THE BOARD<br />
CASE : Cadangan Projek Penjara Reman (Tegar) Fasa 2 di Mukim Pulai Daerah<br />
Johor Bahru, Johor Darul Takzim<br />
COMPLAINANT<br />
: AHAR Consultants Sdn Bhd<br />
RESPONDENT : AYA <strong>Engineers</strong> Sdn Bhd<br />
INVESTIGATING<br />
COMMITTEE<br />
FACT OF THE<br />
CASE<br />
: Ir. Fong Tian Yong (Chairman)<br />
YBhg. Dato’ Ir. Kok Soo Chon<br />
Ir. Rocky HT Wong<br />
<strong>AGENDA</strong> <strong>3.1.2</strong><br />
: Background<br />
The complainant AHAR is the M&E consultant for phase 1 <strong>of</strong> the above<br />
project appointed by the D&B Contractor ISTS-JV on 2007. Before the<br />
construction works for phase 1 ended on April 2011, they claimed to have<br />
received instruction from JKR, the project Director to proceed with phase 2<br />
M&E design on June 2010. They claimed to have completed the design<br />
and tender documentation by Dec 2010 and submitted to JKT HODT<br />
(Head <strong>of</strong> Design Team).<br />
However, on Mac 2011, they were informed that phase 2 project was<br />
awarded to the same Contractor as D&B contract and the contractor has<br />
submitted new M&E consultant, AYA as the M&E consultant.<br />
As such, AHAR regarded that such appointment as supplanting as they<br />
are sure that AYA would have known AHAR involvement during phase 1.<br />
They regard such action as supplanting and/or attempt to supplant and this<br />
has contravened the BEM pr<strong>of</strong>essional etiquette.<br />
IC’s findings<br />
a) There was no dispute that the D&B contractor has only appointed one<br />
M&E consultant for phase 2 i.e. AYA. AYA has also sought the<br />
reconfirmation from D&B contractor that they are the only M&E<br />
consultant appointed for phase 2 <strong>of</strong> the project in writing before<br />
accepting the appointment.<br />
b) JKR pro-active step in assuming the method <strong>of</strong> future contract (phase<br />
2) and requesting informally the Complainant in performing some the<br />
M&E design works for phase 2 may have mis-led them into thinking that<br />
they will be appointed eventually. The Complainant admitted that they<br />
assumed some risk when they perform the design works before any<br />
<strong>of</strong>ficial appointment.<br />
c) It is very clear from the above that the element <strong>of</strong> supplanting does not<br />
exist at all since the client has not appointed any one before appointing<br />
the Respondent AYA for M&E works for phase 2. Appointment <strong>of</strong> phase<br />
1 cannot be linked to Phase 2 as far as design works is concerned as<br />
they are separate matter.<br />
____________________________________________________________________________<br />
IC’s RECOMMENDATION<br />
The IC recommended that there shall be no charge to be taken against the Respondent,<br />
namely AYA <strong>Engineers</strong> Sdn Bhd.
Page 1 <strong>of</strong> 22
Page 2 <strong>of</strong> 22
Page 3 <strong>of</strong> 22
Page 4 <strong>of</strong> 22
Page 5 <strong>of</strong> 22
Page 6 <strong>of</strong> 22
Page 7 <strong>of</strong> 22
Page 8 <strong>of</strong> 22
Page 9 <strong>of</strong> 22
Page 10 <strong>of</strong> 22
Page 11 <strong>of</strong> 22
Page 12 <strong>of</strong> 22
Page 13 <strong>of</strong> 22
Page 14 <strong>of</strong> 22
Page 15 <strong>of</strong> 22
Page 16 <strong>of</strong> 22
Page 17 <strong>of</strong> 22
Page 18 <strong>of</strong> 22
Page 19 <strong>of</strong> 22
Page 20 <strong>of</strong> 22
Page 21 <strong>of</strong> 22
Page 22 <strong>of</strong> 22