ENVIRONMENTAL SCOPING REPORT FOR THE PROPOSED 40MW OPEN CYCLE GAS TURBINE POWER<br />
PLANT IN THE AMERSFOORT AREA, MPUMALANGA<br />
Bohlweki-SSI Environmental<br />
Table 11.3: Key milestones of the programme for the EIA phase of the<br />
project<br />
KEY MILESTONE ACTIVITY PROPOSED<br />
DATE<br />
COMPLETION<br />
Undertake further public participation – public<br />
meetings and focus group meetings,<br />
October 2009<br />
Finalisation of Environmental Scoping Report November 2009<br />
DW&EA acceptance of the Environmental Scoping<br />
Report and Plan of Study to undertake the<br />
Environmental Impact Assessment<br />
Mid-January 2010<br />
Undertake detailed specialist studies November 2009 – January 2010<br />
Compile draft EIA Report and draft EMP November 2009 – March 2010<br />
Making draft EIA Report and draft EMP available<br />
to the public, stakeholders and authorities<br />
March – April 2010<br />
Submit final EIA Report and EMP to authorities April 2010<br />
Authority review period April – August 2010<br />
Issuing of authorisation (positive or negative) Mid-August 2010<br />
Notify I&APs of authorisation Mid-August 2010<br />
11.10. Environmental Study Team<br />
Details of the environmental study team and their fields of specialisation are provided<br />
in Table 11.4 below.<br />
Table 11.4 Proposed specialist team and their areas of expertise<br />
NAME AND ORGANISATION<br />
SPECIALIST STUDY TO BE<br />
UNDERTAKEN DURING EIA PHASE<br />
Malcolm Roods - Bohlweki-SSI Project Director for the EIA process;<br />
Environmental<br />
review and quality control of EIA<br />
process documentation.<br />
Prashika Reddy - Bohlweki-SSI Project Manager for the EIA process.<br />
Environmental<br />
Management of specialist team.<br />
Compilation of all project<br />
documentation; assistance in public<br />
participation.<br />
Sibongile Hlomuka - Bohlweki-SSI Project Manager for the public<br />
Environmental<br />
participation process.<br />
Yolisa Zokufa - Bohlweki-SSI Environmental Assistance with the public participation<br />
process.<br />
Reinie Meyer - Private Peer review of geohydrology<br />
Chris Waygood – Jones and Wagner<br />
assessment<br />
Peer review of hydrology assessment<br />
Paul da Cruz – SiVEST Wetland delineation study<br />
Dr Johan van der Waals - Terra Soil Science Soils and Agricultural Potential<br />
Riaan Robbeson and Dewald Kamfer - Ecological assessment (flora and fauna)<br />
Bathusi Environmental Consulting (BEC)<br />
E02.JNB.000308<br />
ESKOM HOLDINGS LIMITED<br />
01<br />
123<br />
08/10/2009