ENVIRONMENTAL SCOPING REPORT FOR THE PROPOSED 40MW OPEN CYCLE GAS TURBINE POWER PLANT IN THE AMERSFOORT AREA, MPUMALANGA<br />
ISSUE AREA OF POTENTIAL IMPACT RECOMMENDATIONS<br />
• Gas released from the stacks of the 40MW OCGT<br />
as well as from the flare of the UCG pilot plant and<br />
safety valves during regular or upset conditions;<br />
• Release of condensate from the processing plant;<br />
• Material transfer operations;<br />
• Wind erosion from exposed storage piles (sand for<br />
construction); and<br />
• Vehicle entrained dust from both paved and<br />
unpaved road surfaces.<br />
The following activities are associated with the<br />
decommissioning phase:<br />
• Existing buildings and structures demolished,<br />
rubble removed and the area levelled;<br />
• Remaining exposed excavated areas filled and<br />
levelled using overburden<br />
• Topsoil replaced using topsoil recovered from<br />
stockpiles; and<br />
• Land and permanent waste piles prepared for revegetation.<br />
Possible sources of fugitive dust emission during the<br />
closure and post-closure phase include:<br />
• Grading of sites;<br />
• Infrastructure demolition;<br />
Bohlweki-SSI Environmental<br />
E02.JNB.000308<br />
ESKOM HOLDINGS LIMITED<br />
01<br />
104<br />
08/10/2009