TOU tariffs (Megaflex, Miniflex <strong>and</strong> Ruraflex) are suitable for customers that are able to<br />
manage their energy consumption according to <strong>Eskom</strong>'s specified time schedule. These<br />
tariffs are available upon conclusion of an electricity supply agreement with <strong>Eskom</strong>.<br />
Existing > 150 kVA customers converting to TOU, where an impact study indicates a<br />
financial saving due to the conversion, will be subject to a conversion surcharge. The<br />
conversion surcharge is calculated as a percentage of the saving arising from the conversion<br />
without load shifting taking place. A 90% conversion surcharge will be applicable to all<br />
conversions for a period of 12 months after conversion, regardless of the year of<br />
conversion. The conversion surcharge will reduce by 18 percentage points after every<br />
completed 12 months; after conversion to TOU. The conversion surcharge will therefore<br />
reduce to 0% once the customer has been on a TOU tariff for five years.<br />
The reduction of the conversion surcharge is indicated below:<br />
Conversion<br />
surcharge<br />
Appendices continued...<br />
Appendix D: TOU conversion surcharge<br />
Months after conversion<br />
1 - 12 13 - 24 25 - 36 37 - 48 49 - 60<br />
90% 72% 54% 36% 18%<br />
ã <strong>Eskom</strong> July <strong>2008</strong> 41