Measurement and Verification Standard <strong>Guideline</strong> for Low Pressure <strong>Solar</strong> <strong>Water</strong> <strong>Heating</strong> Systems v1r1<br />
Figure 18: Complete Installation of a dedicated SWH Data Logger at a RDP House<br />
6.4 Base Line Methodology<br />
As elaborated in Section 3.3. above the LPSWH systems will be treated as Retrofit Projects,<br />
thus the system (electric water heating at the houses) physically exist and can consequently<br />
be measured and monitored before it is altered by the EEDSM project (the installation of<br />
the LPSWHs). Thus, the base line is determined on the basis of hot water usage heated by<br />
ELECTRICITY ONLY i.e. what the grid would “see”.<br />
6.4.1 Base Line Main M&V Question<br />
The main M&V question when dealing with LPSWH projects is to identify the electricity<br />
consumption and its time of use to heat water prior the retrofit. This may be achieved by<br />
the following ways:<br />
By interviews with the inhabitants<br />
By dedicated SWH measurements after the retrofit<br />
By measurements of the electricity prior and after retrofit.<br />
6.4.2 Interviews with the inhabitants<br />
This method provides information on the following activities as summarised in Table 8.<br />
Table 8: Possible Information obtained by interviews by the occupants of the households.<br />
No Information Obtained Remarks<br />
1 Number of people living in the house (their profile:<br />
gender, age, working , unemployed, culture etc.)<br />
29<br />
Often people are giving misleading<br />
and inconsistent information. Also