Overview of <strong>Multi</strong>-<strong>Year</strong> <strong>Price</strong> <strong>Determination</strong><br />
2013/14–2017/18 (MYPD 3)<br />
Page 98 of 144<br />
to Operating costs in Moving towards a sustainable electricity industry for projections on<br />
primary energy and nuclear energy costs.)<br />
The sales forecast for MYPD 3 was compiled in consultation with key customers and<br />
representatives from customer groups to determine their expected energy requirements. It<br />
projects that sales growth will slow to 1.9% a year for the five years of the proposed MYPD<br />
period, compared with the 2.8% growth projected in the MYPD 2 application.<br />
Projected sales volumes represent net sales after accounting for IDM initiatives (see Table<br />
40). As mentioned, the MYPD 2 sales forecast for 2013/14 to 2017/18 was significantly<br />
higher than the MYPD 3 sales forecast.<br />
Table 40: MYPD 2 actual sales and sales projections versus MYPD 3 sales projections (net of<br />
IDM initiatives)<br />
2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18<br />
MYPD 2 application (GWh) 228 266 233 400 237 932 242 472 246 494 254 140 263 325 272 560<br />
Growth in MYPD 3 forecasts (%) 2.2% 1.9% 1.9% 1.7% 3.1% 3.6% 3.5%<br />
MYPD 3 application (GWh) 224 446 225 130 222 028 227 404 229 513 235 638 239 112 244 026<br />
Growth in MYPD 3 forecasts (%) 0.3% -1.4% 2.4% 0.9% 2.7% 1.5% 2.1%<br />
Decline in sales compared to MYPD 2 (GWh) 3 820 8 270 15 904 15 068 16 981 18 502 24 213 28 534<br />
Table 41: Summary of IDM costs and energy savings<br />
The energy requirements in the sales forecast will be served by:<br />
<strong>Eskom</strong>‟s current power stations, based on EAF projections that assume all<br />
planned maintenance will be done.<br />
Power stations that will be commissioned within the MYPD 3 period as part of the<br />
current capacity expansion programme.<br />
Known and signed non-<strong>Eskom</strong> generators (for instance, those owned by<br />
municipalities).<br />
2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 MYPD 3<br />
Programmes - peak demand savings (MW) 344 343 1 286 458 358 221 232 461<br />
Programmes - annualised energy savings (GWh) 1 274 1 334 3 505 2 245 1,361 826 1 016 2 283<br />
Programmes - costs (Rm) 576 1 593 7 485 2 660 2,419 1 581 1 652 3 033 11 345<br />
Operating costs (Rm) 246 485 309 463 480 484 518 580 2 525<br />
Depreciation (Rm) 1 4 1 1 1 1 1 1 5<br />
Total costs (Rm) 823 2 082 7 795 3 124 2 900 2 066 2 171 3 614 13 875<br />
Other (Rm) - 44 - 140 - 11 - 183 - 191 - 204 - 205 - 2 - 785<br />
Net costs (Rm) 779 1 942 7 784 2 941 2 709 1 862 1 966 3 612 13 090<br />
Known and signed IPPs, including renewable energy IPPs.