Accomplishments during MYPD 2<br />
Overview of <strong>Multi</strong>-<strong>Year</strong> <strong>Price</strong> <strong>Determination</strong><br />
2013/14–2017/18 (MYPD 3)<br />
Page 41 of 144<br />
Keeping the lights on. There has been no load-shedding since April 2008. This<br />
achievement is the result of the effective management of <strong>Eskom</strong>‟s system operator and its<br />
generation capacity and operations, coupled with the purchase of some capacity from<br />
independent producers and with expanded initiatives to manage demand and raise<br />
awareness of the need for businesses and households to use electricity more efficiently.<br />
Electrification. The electrification programme has connected more than 4.2 million<br />
households to the electricity grid since it was launched in 1991.<br />
Progress on the capacity expansion programme. The first boiler at Kusile power station<br />
is under construction and will start generating power from the end of 2014. Medupi power<br />
station is on track to deliver first power to the grid in 2013. The Grootvlei power station has<br />
been returned to service, along with an additional three units at Komati power station (the<br />
remaining three are expected to be commissioned by 31 March 2013). The capacity<br />
expansion programme met its key performance targets during the period. A total of 850MW<br />
was added to the system in the first two years of MYPD 2 and a further 260MW is projected<br />
to be added by the end of the period. Since 2005, 4 164km of transmission network and<br />
about 20 195 MVA of substations have been installed.<br />
Strengthening financial sustainability. <strong>Eskom</strong> earned a surplus that will be used to reduce<br />
debt and fund capital expansion over the next five years. Net profit for the year ending<br />
31 March 2012 was R12.7 billion (2010/11: R7.9 billion). The company‟s cash reserves<br />
remain healthy. By 31 March 2012, <strong>Eskom</strong> had secured more than 77% of the R333 billion<br />
funding required for the capital expansion programme.<br />
Improving operational efficiency. The company has completed the first phase of its Back-<br />
to-Basics programme – a performance-improvement initiative to standardise, simplify and<br />
optimise processes and systems. This has already yielded in excess of R4.5 billion in<br />
savings.<br />
Enhancing environmental protection and mitigating the effects of climate change.<br />
Construction on the Sere renewable energy wind project in the Western Cape is expected to