Overview of <strong>Multi</strong>-<strong>Year</strong> <strong>Price</strong> <strong>Determination</strong><br />

2013/14–2017/18 (MYPD 3)<br />

Findings of scenario 2 <strong>Eskom</strong> builds 100% of IRP 2010 post MYPD3<br />

A representation of the capacity allocations is presented in the figure below:<br />

Figure 14: Allocation of the IRP 2010 capacity on the <strong>Eskom</strong> 100% build scenario<br />

Page 116 of 144<br />

The results of the capacity allocations for the 100% scenario show that the additional<br />

2700MWs built by <strong>Eskom</strong> has an incremental impact on the capital expenditure of an<br />

additional R57bn. This is further illustrated in Table 51.