3. Section-500<br />

3. The primer should be sprayed uni<strong>for</strong>mly over the dry surface of absorbent granular base, using<br />

suitable bitumen pressure distributor or sprayer capable of spraying primer at specified rates and<br />

temperature so as to provide a uni<strong>for</strong>mly unbroken spread of primer. Normal temperature range<br />

of spraying emulsion should be 20°C to 60°C. The rate of application depends upon the porosity<br />

characteristics of the surface to be primed and is given in Table 502.1<br />

TABLE 502.1: RATE OF APPLICATION OF BITUMINOUS EMULSION FOR PRIME COAT<br />

Porosity Type of surface Viscosity at 60°C Rate of<br />

Kinematic Saybolt Furol application per<br />

Viscosity<br />

(Centistokes)<br />

(seconds) 10 sq m(kg)<br />

Low WMM/ WBM 30 – 60 14 –28 6 – 9<br />

Medium Cement stabilized 70 – 140 33 – 66 9–12<br />

soil base<br />

High Gravel base 250 – 500 117 - 234 12- 15<br />

4. A very thin layer of coarse sand may be applied to the surface of the primer to prevent it from<br />

getting picked up under the wheels of vehicles delivering materials <strong>for</strong> construction of bituminous<br />

layer<br />

5. The surface should be allowed to cure preferably <strong>for</strong> 24 hours. Unabsorbed primer should be<br />

blotted with sand using the minimum quantity possible.<br />

B. <strong>Quality</strong> Control Requirements<br />

1. The viscosity requirements <strong>for</strong> bitumen emulsion will depend upon the type of surface as already<br />

given in Table 502.1.<br />

2. A priming grade bitumen emulsion (slow setting ) con<strong>for</strong>ming to IS:8887 should be used.<br />

3. <strong>Quality</strong> Control Tests:<br />

3.1 Tests Prior to Construction<br />

The quality control tests to be carried out prior to construction are indicated in Table 502.2. These<br />

tests shall be carried out on the bitumen binders (Emulsion/Cutback) brought on the site by the<br />

Contractor <strong>for</strong> use in the work.<br />

TABLE 502.2: QUALITY CONTROL TESTS PRIOR TO CONSTRUCTION<br />

Type of Test Frequency<br />

1. Viscosity (using Saybolt Furol Viscometer) (IS:8887) One test <strong>for</strong> each lot<br />

2. Residue on 600 micron sieve (IS:8887) -do-<br />

3. Storage Stability Test (IS:8887) -do-<br />

4. Flash Point Test, where bituminous cutback is to be used (IS:217) -do-<br />

5. Viscosity Test (IS:217), where bituminous cutback is to be used -do-<br />

86