3. Section-400<br />
409. LIME-FLYASH STABILIZED SOIL SUB-BASE<br />
The Lime-Flyash Stabilized Soil is a mixture of soil and flyash, when stabilized with lime.<br />
A. Methodology<br />
1. Be<strong>for</strong>e receiving the lime-flyash stabilized soil sub-base, the subgrade should be shaped to the<br />
desired profile and checked <strong>for</strong> line, grade and cross-section. Any irregularities beyond the<br />
permitted tolerance, soft and yielding spots should be corrected and adequately compacted.<br />
2. The soil free from any organic or deleterious material should con<strong>for</strong>m to the pulverization<br />
requirements as under:<br />
Percent weight of soil passing IS Sieve 26.5 mm - 100%<br />
Percent weight of soil passing IS Sieve 5.6 mm - 80%<br />
Where required, suitable equipment like tractor-towed disc harrows should be deployed <strong>for</strong><br />
meeting the pulverization requirements.<br />
3. On the prepared sub-grade, the pulverized soil should be spread uni<strong>for</strong>mly, the uncompacted<br />
thickness being about one-third more than the specified compacted thickness, determined through<br />
field trials.<br />
4. Lime and Flyash in the required quantities should be spread uni<strong>for</strong>mly over the soil, taking care<br />
to prevent raising of dust.<br />
5. A tractor-towed Rotavator or similar equipment should be used <strong>for</strong> mixing. The process of mixing<br />
should be continued till the required uni<strong>for</strong>mity of mixing has been obtained.<br />
6. Prior to compaction, the specified moisture content should be (±) 2 percent of the optimum moisture<br />
content. Where required, water should be added uni<strong>for</strong>mly using a Water Bowser fitted with a<br />
Sprinkler.<br />
7. Water should be uni<strong>for</strong>mly mixed with the soil-lime-flyash mix by discing or harrowing using<br />
tractor-towed disc harrows or similar equipment.<br />
8. Manual mixing, when permitted by the Engineer shall be carried out as per Clause 409.5.4 of<br />
MoRD Specifications.<br />
9. Immediately after spreading, grading and leveling of the mixed material, compaction should be<br />
carried out, till 100% of the maximum dry density of the material as per IS:2720 Part 7 is achieved.<br />
10. Not more than 60 minutes should elapse between the start of moist mixing and start of the<br />
compaction process. Normally, compaction should be completed within 3 hours of mixing.<br />
11. Curing of the compacted layer should be carried out <strong>for</strong> a minimum period of 7 days by spreading<br />
moist straw/wet gunny bags or sand and periodically sprinkling water.<br />
12 At the end of the day’s work, a transverse construction joint <strong>for</strong> full depth should be made by<br />
chamfering at an angle of 30 0 .<br />