Quality Assurance Handbook for Rural Roads Volume-I - pmgsy

Quality Assurance Handbook for Rural Roads Volume-I - pmgsy Quality Assurance Handbook for Rural Roads Volume-I - pmgsy

18.08.2013 Views

3. Section-1600 C. Do’s and Don’ts Do’s Don’ts 1. Take precautions for safe guarding the environment (Clause 110 of MoRD Specifications) 2. Take appropriate measures to ensure stability of slopes during construction. Provide the necessary protective measure for safety against erosion, subsidence and recurrent slips and slides. Provide apron below the outlet point of culvert where height of waterfall is liable to cause erosion. 3. Ensure that safety measures including traffic signs, guideposts, railings, parapets are provided at appropriate places. 4. Safeguard the Reference Pillars till the completion of work 5 Identify areas for proper disposal of debris and waste materials before commencement of the work 6. At hairpin bends, pave the entire roadway width to avoid erosion. 7. Provide one cross drain on upper arm of hair pin bend just before the bend to minimize flow of water along the surface of the road. 8. If hill cutting is done by manual labour, then start from back cutting line proceeding outwards to valley face otherwise it will be difficult to rectify the defects left in back-cutting. 9. Always prepare completion plans of completed lengths and compare it with original drawings enclosed with the agreement in regard to widths, curves, camber, super elevation and the longitudinal gradient as per Para 1603.8.1 of “ Specifications for Rural Roads”. 10. Carry out the backfill behind retaining wall/breast wall only after the masonry work of wall has been approved by the Engineer. 11. Ensure proper longitudinal gradient as per drawings and all vertical bumps in grades have been removed. 12. Excavate the hill side drain along with hill side cutting work as per Para 1606.1.3 of MORD Specifications. Keep the bed level of side Drain at least 300 mm below the Subbase or drainage layer or as per desired specifications. 13. Construct the cross drainage works like scuppers or small culverts alongwith the formation cutting work. Excavation for catch pit should also be done simultaneously. 14. Salvage serviceable materials and stack at the earmarked location. 1. Do not throw debris from excavation/blasting haphazardly down the hill slope. 2. Do not carry out blasting operation indiscriminately. 3. Do not provide Hair Pin bends at inner curves. Locate them at stable places having gentle hill slope requiring lesser height of retaining walls and lesser height of back cutting 4. Do not stack serviceable stones over Roadway so as to allow free flow of traffic. 5. Do not allow debris lying along the road. 6. Do not allow bumps or steep grades or reverse grades in longitudinal section of hill roads. 7. Do not construct retaining walls, which are having outer curve in plan, specially at hairpin bends. These are weaker in regard to stability and are easily liable to collapse. Better break such as walls into segments to avoid their bulging tendency. 8. Do not allow gradient defects to continue. These must be got rectified otherwise these will remain for the whole life of the road. 9. Do not spread the aggregate in very very small stretches. This may adversely affect the riding quality of the surface. 10. Do not allow construction of Retaining walls until proper road geometrics has been achieved in hillcutting otherwise this may lead to excessive heights and quantities of R wall masonary creating unnecessary cost escalation. 11. Do not allow any pilferage of reference level pillars & back reference pillars. Keep a watch and ward on reference pillars. If a few level pillars are raised by about one metre in a continuous stretch, same geometrics can be achieved. But this will adversely affect the adjoining jobs where steeper gradient will occur. Similarly if back-cutting line is shifted to 1.0 m in front, it will be difficult to judge its correctness but its overall effects will be less height of cutting and much more quantity of retaining walls may cause huge cost escalation. 12. Do not allow gradient steeper than permissible at hairpin bends. Flatter gradients are always preferable to steeper gradients at such locations. 13. Do not consider the hill road as complete until it has been properly compared with the contract drawings in regard to curve radius & gradient. 222

SECTION 1700 TRAFFIC SIGNS, 223 Quality Assurance Handbook for Rural Roads MARKINGS & OTHER ROAD APPURTENANCES

3. Section-1600<br />

C. Do’s and Don’ts<br />

Do’s Don’ts<br />

1. Take precautions <strong>for</strong> safe guarding the environment<br />

(Clause 110 of MoRD Specifications)<br />

2. Take appropriate measures to ensure stability of<br />

slopes during construction. Provide the necessary<br />

protective measure <strong>for</strong> safety against erosion,<br />

subsidence and recurrent slips and slides. Provide<br />

apron below the outlet point of culvert where height<br />

of waterfall is liable to cause erosion.<br />

3. Ensure that safety measures including traffic signs,<br />

guideposts, railings, parapets are provided at<br />

appropriate places.<br />

4. Safeguard the Reference Pillars till the completion<br />

of work<br />

5 Identify areas <strong>for</strong> proper disposal of debris and waste<br />

materials be<strong>for</strong>e commencement of the work<br />

6. At hairpin bends, pave the entire roadway width to<br />

avoid erosion.<br />

7. Provide one cross drain on upper arm of hair pin<br />

bend just be<strong>for</strong>e the bend to minimize flow of water<br />

along the surface of the road.<br />

8. If hill cutting is done by manual labour, then start<br />

from back cutting line proceeding outwards to valley<br />

face otherwise it will be difficult to rectify the defects<br />

left in back-cutting.<br />

9. Always prepare completion plans of completed<br />

lengths and compare it with original drawings<br />

enclosed with the agreement in regard to widths,<br />

curves, camber, super elevation and the longitudinal<br />

gradient as per Para 1603.8.1 of “ Specifications <strong>for</strong><br />

<strong>Rural</strong> <strong>Roads</strong>”.<br />

10. Carry out the backfill behind retaining wall/breast<br />

wall only after the masonry work of wall has been<br />

approved by the Engineer.<br />

11. Ensure proper longitudinal gradient as per drawings<br />

and all vertical bumps in grades have been removed.<br />

12. Excavate the hill side drain along with hill side<br />

cutting work as per Para 1606.1.3 of MORD<br />

Specifications. Keep the bed level of side Drain at<br />

least 300 mm below the Subbase or drainage layer<br />

or as per desired specifications.<br />

13. Construct the cross drainage works like scuppers or<br />

small culverts alongwith the <strong>for</strong>mation cutting work.<br />

Excavation <strong>for</strong> catch pit should also be done<br />

simultaneously.<br />

14. Salvage serviceable materials and stack at the<br />

earmarked location.<br />

1. Do not throw debris from excavation/blasting<br />

haphazardly down the hill slope.<br />

2. Do not carry out blasting operation indiscriminately.<br />

3. Do not provide Hair Pin bends at inner curves. Locate<br />

them at stable places having gentle hill slope requiring<br />

lesser height of retaining walls and lesser height of back<br />

cutting<br />

4. Do not stack serviceable stones over Roadway so as to<br />

allow free flow of traffic.<br />

5. Do not allow debris lying along the road.<br />

6. Do not allow bumps or steep grades or reverse grades<br />

in longitudinal section of hill roads.<br />

7. Do not construct retaining walls, which are having<br />

outer curve in plan, specially at hairpin bends. These<br />

are weaker in regard to stability and are easily liable<br />

to collapse. Better break such as walls into segments<br />

to avoid their bulging tendency.<br />

8. Do not allow gradient defects to continue. These must<br />

be got rectified otherwise these will remain <strong>for</strong> the<br />

whole life of the road.<br />

9. Do not spread the aggregate in very very small<br />

stretches. This may adversely affect the riding quality<br />

of the surface.<br />

10. Do not allow construction of Retaining walls until<br />

proper road geometrics has been achieved in hillcutting<br />

otherwise this may lead to excessive heights<br />

and quantities of R wall masonary creating<br />

unnecessary cost escalation.<br />

11. Do not allow any pilferage of reference level pillars &<br />

back reference pillars. Keep a watch and ward on<br />

reference pillars. If a few level pillars are raised by<br />

about one metre in a continuous stretch, same<br />

geometrics can be achieved. But this will adversely<br />

affect the adjoining jobs where steeper gradient will<br />

occur. Similarly if back-cutting line is shifted to 1.0 m<br />

in front, it will be difficult to judge its correctness but<br />

its overall effects will be less height of cutting and much<br />

more quantity of retaining walls may cause huge cost<br />

escalation.<br />

12. Do not allow gradient steeper than permissible at<br />

hairpin bends. Flatter gradients are always preferable<br />

to steeper gradients at such locations.<br />

13. Do not consider the hill road as complete until it has<br />

been properly compared with the contract drawings<br />

in regard to curve radius & gradient.<br />

222

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!