3. Section-1600<br />

The prescribed roadway width <strong>for</strong> hilly terrain is inclusive of parapet and hillside drains.<br />

Extra widening on curves and in snow bound areas should be done as per Drawings.<br />

(iv) Resort to slope benching to improve sight distance.<br />

(v) Make provision <strong>for</strong> 2 to 3 passing places per kilometre length.<br />

(vi) Where hairpin bends are to be provided, ensure that the hill slopes are stable and gentle.<br />

The hairpin bend will be provided as a circular curve with transitions at either end.<br />

(vii) Follow procedure and safety precautions <strong>for</strong> rock cutting as per Sub-section 304.<br />

(viii) Ensure that excavation work starts along back cutting line. Also ensure that completion<br />

plan and verification of curve radii and longitudinal gradients is carried out at site. Defects<br />

if any shall be corrected immediately.<br />

4. Preparation of cut <strong>for</strong>mation <strong>for</strong> Subgrade<br />

Prepare as per the requirements of Sub-section 302.<br />

5. Retaining Walls, Breast Walls and Gabion structures<br />

(i) Construct retaining/breast walls, and Gabion structures, con<strong>for</strong>ming to the Drawings.<br />

(ii) The foundation bed should be sloped towards the hillside.<br />

(iii) Resort to stepping up of the foundation bed of retaining walls in stable rocks.<br />

(iv) The masonry <strong>for</strong> retaining/breast walls should con<strong>for</strong>m to Sub-section 700.<br />

(v) Ensure that the top level of the retaining wall matches the adjoining shoulder edge.<br />

(vi) Ensure that full section is constructed as per the drawings.<br />

(vii) Ensure that approved filter material is provided behind the wall be<strong>for</strong>e back filling. Also<br />

ensure that back filling is done only after the masonry work is approved by the Engineer.<br />

6. Pavement Construction<br />

Prepare subgrade to the requirements of Subsection 303 and construct subbase, base and bituminous<br />

surfacing in accordance with the requirements of the respective subsections.<br />

7. Drainage<br />

Carry out excavation <strong>for</strong> drains alongwith hillside cutting con<strong>for</strong>ming to the shape, size and grades<br />

as shown on the drawings.<br />

(i) Provide lining as specified.<br />

(ii) Locate catchwater drains over stable slopes outside the periphery of the slide area.<br />

8. Cross Drainage Works<br />

(i) Use locally available stone <strong>for</strong> construction of Scuppers with dry stone masonry. Ensure a<br />

minimum cushion of 600 mm over corbelling, con<strong>for</strong>ming to Clause 1606.5 of MORD<br />

Specification.<br />