Quality Assurance Handbook for Rural Roads Volume-I - pmgsy
Quality Assurance Handbook for Rural Roads Volume-I - pmgsy Quality Assurance Handbook for Rural Roads Volume-I - pmgsy
SECTION 1200 167 Quality Assurance Handbook for Rural Roads RCC SLAB CULVERTS AND MINOR BRIDGES
1200: RCC SLAB CULVERTS AND MINOR BRIDGES General 169 Quality Assurance Handbook for Rural Roads A culvert is a cross drainage structure having a total length of 6 m or less between the inner faces of dirt walls or extreme ventway boundaries measured at right angles. A minor bridge is a bridge having a total length upto 60 m. A small bridge is a bridge where the overall length of bridge between the inner faces of dirt walls is upto 30 m and where individual span is not more than 10 m. In rural roads, individual span lengths upto 15 m are used exceptionally. In this section different items of RCC solid slabs, box culverts, and composite bridges have been dealt with. The cross sections of foundations, substructures such as abutments, return walls besides design of superstructure, drainage spouts, railings, parapets etc. and all other details shall be strictly in accordance with contract documents. For minor bridges having overall length of 30 m and above, a method statement for construction indicating items (a) to (j) as per clause 1201 (xi) of MoRD Specifications for Rural Roads, shall be submitted. A. Methodology A1 Foundations 1. Take the minimum depth of foundation upto the stratum having specified bearing capacity shown on drawing but not less than 2 m below the scour level where no bed protection is provided or 1.5 m below the protected bed level. 2. In case of rocky bed, ensure embedment of foundation into the rock below, the minimum depth being 500 mm for hard rocks and 1200 mm for soft erodible rocks. 3. Provide 300 mm thick plain concrete M15 grade footing, unless otherwise specified on the drawings. Provide a minimum offset of 150 mm for the base of substructure. 4. Set out plan dimension of the foundation at the bottom of foundation trench and check with respect to original reference line and axis. 5. Before laying foundation concrete, clean the earth surface of all loose material and sprinkle water to wet. Provide side formwork as per required dimensions and height. 6. Lay foundation concrete continuously to the required thickness upto the level of construction joint proposed. 7. Finish the concrete surface smooth with a trowel and ensure curing as specified in Section 800. 8. Carryout dewatering where necessary for laying of concrete so as to keep the water level below foundation level with adequate provisions/ precautions. 9. Remove loose sand laid on foundation before commencement of back filling. Refill all spaces excavated and not occupied by permanent work with earth upto surface of surrounding ground. In case of excavation in rock, fill the circular space with M15 concrete.
- Page 110 and 111: 3. Section-500 (ii) Immediately the
- Page 112 and 113: 3. Section-500 512. MODIFIED BITUME
- Page 114 and 115: 3. Section-500 TABLE 512.5 : REQUIR
- Page 116 and 117: Annex-III & IV DETERMINATION OF IN-
- Page 118 and 119: SIMPLE/HANDFEEL TESTS 600 600.1 Bri
- Page 120 and 121: 119 Quality Assurance Handbook for
- Page 122 and 123: SECTION 600 121 Quality Assurance H
- Page 124 and 125: 3. Section-600 4. Build the courses
- Page 126 and 127: 3. Section-600 (v) Storage of mater
- Page 128 and 129: 3. Section-600 3.3. Quality Control
- Page 130 and 131: 700 : STONE MASONRY FOR STRUCTURES
- Page 132 and 133: (v) Stone Masonry 133 Quality Assur
- Page 134 and 135: 4.2. Tests / checks during construc
- Page 136 and 137: SECTION 800 CONCRETE FOR STRUCTURES
- Page 138 and 139: 3. Section-800 2. Proceed with conc
- Page 140 and 141: 3. Section-800 TABLE 800.3: REQUIRE
- Page 142 and 143: 3. Section-800 c. The strength of a
- Page 144 and 145: 3. Section-800 4.2 Tests / checks d
- Page 146 and 147: SECTION 900 149 Quality Assurance H
- Page 148 and 149: 3. Section-900 2. Lower centering g
- Page 150 and 151: 3. Section-900 C. Do’s and Don’
- Page 152 and 153: 1000 STEEL REINFORCEMENT A. Methodo
- Page 154 and 155: 3.2 Tests during construction 159 Q
- Page 156 and 157: 1100: PIPE CULVERTS A. Methodology
- Page 158 and 159: 165 Quality Assurance Handbook for
- Page 162 and 163: 3. Section-1200 A2 Substructures Th
- Page 164 and 165: 3. Section-1200 4. Provide 75 mm ce
- Page 166 and 167: 3. Section-1200 (2) Tolerances 1200
- Page 168 and 169: 3. Section-1200 3.2 Tests / checks
- Page 170 and 171: SECTION 1300 179 Quality Assurance
- Page 172 and 173: 3. Section-1300 A-3 Toe Protection
- Page 174 and 175: 3. Section-1300 2. Stones for pitch
- Page 176 and 177: SECTION 1400 187 Quality Assurance
- Page 178 and 179: 3. Section-1400 3. Give streamline
- Page 180 and 181: 3. Section-1400 2. Tests during con
- Page 182 and 183: SECTION 1500 195 Quality Assurance
- Page 184 and 185: 3. Section-1500 5 Mark location and
- Page 186 and 187: 3. Section-1500 (iv) Water Water us
- Page 188 and 189: 3. Section-1500 TABLE 1501.3: QUALI
- Page 190 and 191: 3. Section-1500 2. Check the in-sit
- Page 192 and 193: 3. Section-1500 TABLE NO. 1502.3: P
- Page 194 and 195: 3. Section-1500 1503: RECTANGULAR C
- Page 196 and 197: 3. Section-1500 3.2 Tests during co
- Page 198 and 199: 3. Section-1500 1504: INTERLOCKING
- Page 200 and 201: 3. Section-1500 2. Quality Control
- Page 202 and 203: SECTION 1600 217 Quality Assurance
- Page 204 and 205: 3. Section-1600 The prescribed road
- Page 206 and 207: 3. Section-1600 C. Do’s and Don
- Page 208 and 209: 1700. TRAFFIC SIGNS AND MARKINGS A.
1200: RCC SLAB CULVERTS AND MINOR BRIDGES<br />
General<br />
169<br />
<strong>Quality</strong> <strong>Assurance</strong> <strong>Handbook</strong> <strong>for</strong> <strong>Rural</strong> <strong>Roads</strong><br />
A culvert is a cross drainage structure having a total length of 6 m or less between the inner faces of dirt<br />
walls or extreme ventway boundaries measured at right angles. A minor bridge is a bridge having a<br />
total length upto 60 m. A small bridge is a bridge where the overall length of bridge between the inner<br />
faces of dirt walls is upto 30 m and where individual span is not more than 10 m. In rural roads, individual<br />
span lengths upto 15 m are used exceptionally.<br />
In this section different items of RCC solid slabs, box culverts, and composite bridges have been dealt<br />
with. The cross sections of foundations, substructures such as abutments, return walls besides design of<br />
superstructure, drainage spouts, railings, parapets etc. and all other details shall be strictly in accordance<br />
with contract documents.<br />
For minor bridges having overall length of 30 m and above, a method statement <strong>for</strong> construction indicating<br />
items (a) to (j) as per clause 1201 (xi) of MoRD Specifications <strong>for</strong> <strong>Rural</strong> <strong>Roads</strong>, shall be submitted.<br />
A. Methodology<br />
A1 Foundations<br />
1. Take the minimum depth of foundation upto the stratum having specified bearing capacity shown<br />
on drawing but not less than 2 m below the scour level where no bed protection is provided or 1.5<br />
m below the protected bed level.<br />
2. In case of rocky bed, ensure embedment of foundation into the rock below, the minimum depth<br />
being 500 mm <strong>for</strong> hard rocks and 1200 mm <strong>for</strong> soft erodible rocks.<br />
3. Provide 300 mm thick plain concrete M15 grade footing, unless otherwise specified on the drawings.<br />
Provide a minimum offset of 150 mm <strong>for</strong> the base of substructure.<br />
4. Set out plan dimension of the foundation at the bottom of foundation trench and check with respect<br />
to original reference line and axis.<br />
5. Be<strong>for</strong>e laying foundation concrete, clean the earth surface of all loose material and sprinkle water<br />
to wet. Provide side <strong>for</strong>mwork as per required dimensions and height.<br />
6. Lay foundation concrete continuously to the required thickness upto the level of construction<br />
joint proposed.<br />
7. Finish the concrete surface smooth with a trowel and ensure curing as specified in Section 800.<br />
8. Carryout dewatering where necessary <strong>for</strong> laying of concrete so as to keep the water level below<br />
foundation level with adequate provisions/ precautions.<br />
9. Remove loose sand laid on foundation be<strong>for</strong>e commencement of back filling. Refill all spaces<br />
excavated and not occupied by permanent work with earth upto surface of surrounding ground.<br />
In case of excavation in rock, fill the circular space with M15 concrete.