3. Section-700<br />

C. Do’s and Don’ts<br />

Do’s Don’ts<br />

1. Fit each stone dry, correct in accuracy by cutting,<br />

be<strong>for</strong>e finally laid in mortar and fixed in bed.<br />

2. Mix mortar thoroughly and pour fluid mortar in<br />

joints.<br />

3. Restrict use of chips to fill interstices<br />

4. Ensure that mortar is confined to joints without<br />

smearing the faces.<br />

5. Protect stone masonry during construction against<br />

rain or frost.<br />

136<br />

1. Do not have any dry or hollow space in masonry nor<br />

use water to push mortar into joints.<br />

2. Do not dress or hammer masonry once placed in<br />

position<br />

3. Do not use quantity of chips more than 20 per cent of<br />

the quantity of stone masonry.<br />

4. Do not use stone masonry arch bridges having span<br />

more than 6 m in seismic zones IV and V