3. Section-500<br />

(ii) Immediately thereafter, spread stone chips over the bitumen layer at a uni<strong>for</strong>m rate,<br />

preferably, with the help of a mechanical grit spreader so as to cover the surface completely.<br />

(iii) Commence rolling with 80-100 kN rollers (3-wheel or tandem type), beginning from the<br />

edge and progressing towards the centre longitudinally. On super elevated portions, rolling<br />

should progress from lower to upper edge parallel to centre line of pavement. If required,<br />

spread additional chips by hand to make up irregularities. Continue rolling operations until<br />

all aggregate particles are firmly embedded and present a uni<strong>for</strong>m closed surface.<br />

2. Type A seal coat with emulsion<br />

(i) Apply emulsion uni<strong>for</strong>mly over the prepared surface by mechanical sprayers.<br />

(ii) Immediately after application of emulsion, spread aggregate uni<strong>for</strong>mly and evenly by<br />

mechanical means;<br />

(iii) Roll the surface following the procedure given in Para 1 (iii) above.<br />

3. Type B seal coat with bitumen<br />

(i) Follow the methodology described in Paras 4 & 5 <strong>for</strong> preparing the premix in Sub-section<br />

508.1<br />

(ii) Roll the surface with 80 to 100 kN roller as per procedure given in Para 8 & 9 of methodology<br />

in Sub-section 508.1<br />

(iii) Continue rolling of the mix until the voids in the bituminous surface are completely sealed<br />

and a smooth and uni<strong>for</strong>m surface is obtained.<br />

4. Type B seal coat with emulsion<br />

Follow the methodology described in Sub-section 508.2 except that <strong>for</strong> small jobs manual mixing<br />

may be required.<br />

5. Type C seal coat<br />

Paras 4 to 7 of Sub-section 508.1 dealing with methodology <strong>for</strong> premix carpet may be referred to<br />

<strong>for</strong> preparation of the mix, spreading and rolling the same.<br />

6. Traffic on Type B and Type C seal coat may be allowed after completion of rolling operations and<br />

the surface is at ambient temperature. Traffic on Type A seal coat may be allowed only on the<br />

following day. In exceptional circumstances the road with Type A seal coat my be opened to<br />

traffic immediately after rolling but the traffic speed should be restricted to 16 km/h until the<br />

following day.<br />

B. <strong>Quality</strong> Control Requirements<br />

1. Materials<br />

(a) Aggregates<br />

Aggregate shall con<strong>for</strong>m to the physical requirements indicated in Table 508.1.2. Quantities<br />

and grading requirements <strong>for</strong> aggregates are given in Table 510.1.<br />

108