No.P-17029/1/2006/P-III<br />
National Rural Roads Development Agency<br />
Ministry of Rural Development<br />
Government of India<br />
#5 th Floor, NBCC Tower,<br />
Bhikaji Cama Place, New Delhi-110066<br />
Dated: 8th March, <strong>2013</strong>.<br />
Sub.: Minutes of Meeting to review progress of the implementation of World Bank<br />
RRP-II in Uttarakhand.<br />
A meeting to review the performance of World Bank RRP II for the State of<br />
Uttarakhand was held on 4 th March, <strong>2013</strong> at NRRDA, New Delhi. List of participants is<br />
enclosed as Annexure I.<br />
1. Approval of DPRs – An entitlement of US $ 276 million (Rs.1228 crore) has<br />
been provided as per the Project Appraisal Document (PAD) of World Bank.<br />
(i) Approval of 36 Nos. of DPRs for 98.11 km amounting to Rs.71.54 crore<br />
was issued in October, 2011 out of which State has withdrawn 7 DPRs for<br />
63.37 km amounting to Rs.27.42 crore. Thus the net approval stands at 29<br />
DPRs for 34.74 km amounting to Rs.44.12 crore.<br />
(ii) Approval of 126 DPRs for 1139.78 km amounting to Rs.471.36 crore has<br />
already been issued in February, <strong>2013</strong>.<br />
(iii) Shri K.K. Jain, Chief Engineer, PMGSY, Uttrakhand informed that 109<br />
DPRs amounting to Rs.336 crore have been submitted in NRRDA within<br />
this week for which pre-EC is to be held. He further promised to submit<br />
100 DPRs for Rs.500 crore and 71 DPRs for Rs.189 crore by 31.3.<strong>2013</strong> and<br />
15.4.13 respectively. The Consultant (WB-I) NRRDA suggested to involve<br />
the recently appointed PMC by the State, at this stage of processing of<br />
DPRs.
2. Work Plan: Chief Engineer, PMGSY Uttarakhand has confirmed receipt of work<br />
plan finalized by NRRDA for the State of Uttarakhand and has also assured that he<br />
would be able to achieve the physical and financial targets as specified in the work<br />
plan.<br />
3. Procurement:<br />
(i) Chief Engineer, PMGSY informed that 15 works for Rs.18.83 crore are in<br />
progress. Balance 14 works are in various stages of tendering including<br />
recall.<br />
(ii) Chief Engineer, PMGSY Uttarakhand further informed that they have<br />
already called tenders for 471 crore for which approval was received in<br />
February, <strong>2013</strong>. He had raised a query regarding single tender which has<br />
been resolved and copy of MoRD letter No.P-17025/43/2011-RC dated<br />
12.12.2011 withdrawing the circular No.11/2011 dated 3.11.2011 was also<br />
handed over to him. Keeping in view the above issue of single tender, Chief<br />
Engineer agreed to award works to the tune of Rs.200 crore within March,<br />
<strong>2013</strong>.<br />
(iii) Chief Engineer has been directed to submit monthly targets for call of<br />
tender, receipt of tender and acceptance of tender by 12 th March, <strong>2013</strong><br />
which shall be reviewed every month by Consultant (WB-I).<br />
4. Physical Progress: In the formats being sent to review Physical and Financial<br />
Progress of roads, status of progress of bridges is not being recorded. Chief<br />
Engineer is advised to record the progress of these bridges by specifying 7-8<br />
milestones for better appreciation of the progress.<br />
5. Financial Progress: The updated expenditure upto January, <strong>2013</strong> was Rs.3.62<br />
crore and Chief Engineer has agreed to enhance this expenditure upto 20 crore by<br />
31 st March, <strong>2013</strong>.<br />
6. OMMAS: Though entries are being made regularly in OMMAS but the same<br />
have not been closed after October, 2012 which is not healthy practice, therefore,<br />
Chief Engineer has agreed to ensure that R&P Module of OMMAS will be
updated latest by 15 th March, <strong>2013</strong>. Shri Ravish Chander, AD (Finance), NRRDA<br />
shall review and report the deficiencies by 31 st March, <strong>2013</strong>.
S.No.<br />
List of Participants<br />
Name and Designation State/Organization<br />
1. Shri Puran Chandra, SE URRDA<br />
2. Shri K. K. Jain, CE PMGSY<br />
3. Col. R Rastogi VSM (Retd.) Meinhardt, Singapore<br />
4. R. K. Bajaj, CGM-BD Meinhardt, Singapore<br />
5. Shri Ravish Chander, AD NRRDA<br />
6. Shri Arvind Singh Jyala URRDA<br />
7. Shri Ramesh Chandra Gupta, EE URRDA<br />
8. Shri S.S. Bhatia NRRDA<br />
9. Shri V.K. Gupta, Consultant (WB-I) NRRDA<br />
10. Lt. Col. Arun Kr. Kher, Consultant (WB-II) NRRDA