RPT - ONE PAGERS - Minnesota State Legislature

RPT - ONE PAGERS - Minnesota State Legislature RPT - ONE PAGERS - Minnesota State Legislature

archive.leg.state.mn.us
from archive.leg.state.mn.us More from this publisher
17.08.2013 Views

From 2.2 Miles east of Hwy. 74 to west Junction Hwy. 43 Eastbound Lanes (St. Charles-Lewiston) State Project No. 8580-156 Schedule: Environmental Document Approval Date: 04/14/2009 Municipal Consent Approval Date: Not Needed Geometric Layout Approval Date: Not Needed Construction Limits Established Date: Original Letting Date: 1/25/2013 Current Letting Date: 2/12/2010 Construction Season: 2010 Estimated Substantial Completion: Fall 2010 Project History: Interstate 90 concrete surface was constructed in 1971. Project Benefits: Improve ride quality, reduce maintenance costs, replace or repair drainage, replace or repair appurtenances. Project Risks: Traffic will be moved to eastbound lanes. Annual Report on Major Highway Projects Minnesota Department of Transportation PROJECT SUMMARY I 90 SUBSTANTIALLY COMPLETE Project Description: Add unbonded concrete overlay to the existing roadway. Saint Charles 11 43 Total Project Cost Estimate (millions) Ingot Dr Iris Rd Fairwater Dr Ibex Rd 305th Ave S Main St Hot Iron Dr Date in which the project entered into the STIP: E 5th St Elba Gunflint Rd Harrow Rd E Center St 325th Ave Goodview Dr Grouse Rd 341st Ave Fern Rd W Center Ave Altura Utica 310th St Echo Rd Flag Rd 290th St 355th Ave Deep River Rd Baseline Est. Current Est. Construction Letting: $ 21.7 $ 15.3 Other Construction Elements: $ 0.0 $ 0.0 Engineering: $ 1.0 $ 1.0 Right of Way: $ 0.0 $ 0.0 Total: $ 22.7 $ 16.3 Construction cost estimates are adjusted to the mid-year of construction, using inflation rates provided by OCPPM. Recent Changes and Updates: This project was advanced due to receiving bond funding. Key Cost Estimate Assumptions: Traffic is assumed to utilize temporary crossovers during construction. 11 21 117 26 119 35 6 39 6 Harrow Rd 108 Heritage Ln Hobbit Ln 37 123 104 115 113 112 33 32 111 286th St Enfield Rd 105 114 14 18 29 381st Ave 27 Doe Rd 109 Williams St Lewiston Minnesota Department of Transportation District 6 2899 48th Street NW (507) 286-7499 District Engineer: Nelrae Succio Project Manager: Jake Rezac Original date of Posting: Jan 2009 Revised Date: 1/15/2011 26 124 33 31 20 Durango Dr 25 106 393rd Ave 340th St Vogen Rd 25 Rollingstone Dunn Ln Airport Dr Airport Rd 25 Ridgeview Rd Peterson 25 2 110 20 120 Rushford Village 23 Indian Chapel Dr Tower Ridge Rd 106 27 Minnesota City Stockton F St Frontage Rd Tuff Ln Oian Rd 102 County Line Rd N Mill St Rushford Aspen Rd 27 Ekern Rd Winona Theurer Blvd 129 12 Goodview 4 26 Winona 21 Page E11 Dump Hill Rd

Schedule: Environmental Document Approval Date: Need Unknown Municipal Consent Approval Date: Need Unknown Geometric Layout Approval Date: Need Unknown Construction Limits Established Date: Need Unknown Original Letting Date: 2018 Current Letting Date: 2018 Construction Season: 2018 Estimated Substantial Completion: Project History: Bridge 6975 was built in 1931 and Bridge 6977 was built in 1924. Both structures are classified as functionally obsolete. Project Benefits: Both bridges have substandard roadway approaches with need for horizontal geometric improvements. This project will improve safety. Project Risks: The roadway approach work could lead to significant environmental issues. It is anticipated traffic will be detoured during construction. Municipal Consent from the City of Lanesboro may be required for Bridge 6975. Annual Report on Major Highway Projects Minnesota Department of Transportation PROJECT SUMMARY Hwy. 250 Replace Bridge 6975 and 6977 Bridge 6975, 6977 Project Description: Replace Bridge 6975, replace Bridge 6977. Total Project Cost Estimate (millions) Date in which the project entered into the STIP: Construction Letting: Other Construction Elements: Engineering: Right of Way: Recent Changes and Updates: New Project Key Cost Estimate Assumptions: 8 21 8 6977 6975 Fillmore Environmental impacts with roadway approach work not significant. Traffic is assumed to be detoured during construction. Municipal Consent from the City of Lanesboro is obtainable, if required for Bridge 6975. Lanesboro Baseline Est. Current Est. 9.0 0.0 1.6 0.5 Total: $ 11.1 Construction cost estimates are adjusted to the mid-year of construction, using inflation rates provided by OCPPM. $ $ $ $ Minnesota Department of Transportation District 6 2900 48th Street NW (507) 286-7500 District Engineer: Nelrae Succio Project Manager: Kjersti Anderson Original date of Posting: Jan 2009 Revised Date: 1/15/2011 Page E12

Schedule:<br />

Environmental Document Approval Date: Need Unknown<br />

Municipal Consent Approval Date: Need Unknown<br />

Geometric Layout Approval Date: Need Unknown<br />

Construction Limits Established Date: Need Unknown<br />

Original Letting Date: 2018<br />

Current Letting Date: 2018<br />

Construction Season: 2018<br />

Estimated Substantial Completion:<br />

Project History:<br />

Bridge 6975 was built in 1931 and Bridge 6977<br />

was built in 1924. Both structures are classified as<br />

functionally obsolete.<br />

Project Benefits:<br />

Both bridges have substandard roadway<br />

approaches with need for horizontal geometric<br />

improvements. This project will improve safety.<br />

Project Risks:<br />

The roadway approach work could lead to<br />

significant environmental issues. It is anticipated<br />

traffic will be detoured during construction.<br />

Municipal Consent from the City of Lanesboro may<br />

be required for Bridge 6975.<br />

Annual Report on Major Highway Projects<br />

<strong>Minnesota</strong> Department of Transportation<br />

PROJECT SUMMARY<br />

Hwy. 250<br />

Replace Bridge 6975 and 6977<br />

Bridge 6975, 6977<br />

Project Description:<br />

Replace Bridge 6975, replace Bridge 6977.<br />

Total Project Cost Estimate (millions)<br />

Date in which the project entered into the STIP:<br />

Construction Letting:<br />

Other Construction Elements:<br />

Engineering:<br />

Right of Way:<br />

Recent Changes and Updates:<br />

New Project<br />

Key Cost Estimate Assumptions:<br />

8<br />

21<br />

8<br />

6977<br />

6975<br />

Fillmore<br />

Environmental impacts with roadway approach work not significant. Traffic is assumed to<br />

be detoured during construction. Municipal Consent from the City of Lanesboro is<br />

obtainable, if required for Bridge 6975.<br />

Lanesboro<br />

Baseline Est. Current Est.<br />

9.0<br />

0.0<br />

1.6<br />

0.5<br />

Total: $ 11.1<br />

Construction cost estimates are adjusted to the mid-year of construction, using inflation rates provided by<br />

OCPPM.<br />

$<br />

$<br />

$<br />

$<br />

<strong>Minnesota</strong> Department of Transportation<br />

District 6<br />

2900 48th Street NW<br />

(507) 286-7500<br />

District Engineer: Nelrae Succio<br />

Project Manager: Kjersti Anderson<br />

Original date of Posting: Jan 2009<br />

Revised Date: 1/15/2011<br />

Page E12

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!