Schedule:<br />

Environmental Document Approval Date: Need Unknown<br />

Municipal Consent Approval Date: Need Unknown<br />

Geometric Layout Approval Date: Need Unknown<br />

Construction Limits Established Date: Need Unknown<br />

Original Letting Date: 2020-2021<br />

Current Letting Date: 2020-2021<br />

Construction Season: 2020-2021<br />

Estimated Substantial Completion:<br />

Project History:<br />

New Project<br />

Project Benefits:<br />

Replace functionally obsolete bridge<br />

Project Risks:<br />

PROJECT SUMMARY<br />

Hwy. 210<br />

Replace Bridge 5060 over Mississippi River in Brainerd<br />

Right of Way Impacts in City of Brainerd<br />

Annual Report on Major Highway Projects<br />

<strong>Minnesota</strong> Department of Transportation<br />

Bridge 5060<br />

<strong>State</strong> Project No. 1805-74<br />

Project Description:<br />

Project was initiated to plan for replacement<br />

of Bridge # 5060. Due to the age of the<br />

bridge, size and cost, it should be included<br />

in the Highway Investment Plan. The deck<br />

geometry and traffic volumes are a safety<br />

problem for motorists and pedestrians.<br />

Crow Wing<br />

Baxter<br />

Total Project Cost Estimate (millions)<br />

Date in which the project entered into the STIP:<br />

Construction Letting:<br />

Other Construction Elements:<br />

Engineering:<br />

Right of Way:<br />

Recent Changes and Updates:<br />

48<br />

49<br />

5<br />

153<br />

20<br />

Brainerd<br />

BR# 5060<br />

Project was delayed one year (to 2020) to address pavement preservation investment<br />

priorities identified in district's highway investment plan.<br />

Key Cost Estimate Assumptions:<br />

Baseline Est. Current Est.<br />

10.0<br />

1.0<br />

1.2<br />

3.0<br />

Total: $ 15.2<br />

Construction cost estimates are adjusted to the mid-year of construction, using inflation rates provided by<br />

OCPPM.<br />

$<br />

$<br />

$<br />

$<br />

<strong>Minnesota</strong> Department of Transportation<br />

District 3<br />

7694 Industrial Boulevard<br />

(218) 828-5700<br />

District Engineer: Robert Busch<br />

Project Manager: Terry Humbert<br />

Original date of Posting: Jan 2010<br />

Revised Date: 1/15/2011<br />

45<br />

3<br />

117<br />

Page C6