After satisfactory test, the contractor shall remove water from the pipeline and clean<br />

it after testing at his own cost, without flooding adjoining areas.<br />

Duration of Hydraulic Test:<br />

The test is for 1 hour only. The rate of allowable leakage is given on per day basis.<br />

The leakage observed within one hour shall be converted to per day basis and<br />

compared with criteria given.<br />

Maximum field test pressure for pipes with flexible joints:<br />

Table : 1 on page 11 of IS:12288 wherever is applicable.<br />

11.8 Interconnection work.<br />

The interconnection work between the existing main and the proposed main to be<br />

laid under this contract shall proceed from the new main to the existing main.<br />

Before actually proceeding with the interconnection work, the Contractor shall<br />

make ready necessary tools and plants required for the work at site, such as pump<br />

sets, shoring materials etc. He shall also keep ready at site necessary pipes, jointing<br />

materials, specials and valves required for the work. The Contractor shall keep<br />

necessary skilled workmen of sufficient strength at site and once the work<br />

commenced, the entire interconnection work shall proceed without interruption by<br />

engaging labour for carrying out the work on a continuous basis both day and night<br />

till the work is completed. The work shall be executed as per programme drawn up<br />

by the Engineer and shall be completed within the time ordered by the Engineer, for<br />

each individual interconnection. The work shall be carried out under the direction<br />

of the Engineer from the beginning to end.<br />

Laying of specials, valves (except straight pipes from the branch of the new main to<br />

the connecting point in the existing main) including conveying specials etc. from<br />

the stores or site of stacking, excavating, timbering, pumping out water from the<br />

trenches, lowering, aligning, jointing specials and valves, cutting the existing mains,<br />

dealing with water, inserting the necessary branches, jointing, testing, refilling etc.<br />

is included in the item of providing, laying and jointing DI/MS pipes. Any ancillary<br />

work either of Temporary or Permanent nature required for interconnection and not<br />

covered by schedules shall be executed by the Contractor at no extra cost.<br />

GTS : General Technical specification. Page 90