2. Where specified, the surface of the set concrete shall be painted with two coats<br />

of an approved bituminous paint, which shall be allowed to dry before placing new<br />

concrete against it. Care shall be taken to prevent paint getting on the water stop, if<br />

any.<br />

3. Expansion joints shall be formed by a separating strip of pre-formed<br />

compressible imperishable joint filler, to be approved by the Engineer.<br />

7.15 Testing of concrete.<br />

Sampling and strength test of concrete shall be as per 14 of IS:456-2000.<br />

GTS : General Technical Specification. Page 66