Weigh-batching: Weigh batching machines shall provide facilities for the accurate<br />

control and measurement of the materials either singly or cumulatively and shall be<br />

capable of immediate adjustment by operators in order to permit variations if<br />

ordered by the Engineer. All weight dials shall be easily visible from the place at<br />

which filling and emptying of the hoppers are controlled.<br />

Addition of water and mixing:<br />

Water: The addition of water to a mixer shall be controlled such that between five<br />

and ten percent of the water enters the mixer before the cement and aggregate and a<br />

further five to ten percent of water enters the mixer after the said materials have<br />

been batched. The remainder of the water shall be added at a uniform rate with the<br />

said materials. The water-measuring device shall also be readily adjustable so that<br />

the quantity of water added to the mixer can, if necessary in the opinion of the<br />

witnessing Engineer’s representative be varied. The natural moisture contents of<br />

the aggregates shall be determined before the commencement of concreting or at<br />

such intervals as may be necessary or as required by the Engineer. The Contractor<br />

shall make due allowance for the water contained in the aggregate when<br />

determining in consultation with the Engineer’s representative, the quantity of water<br />

to be added to each mix, and shall adjust the amount of water added to each mix to<br />

maintain consistently the approved water/cement ratio of the mixed concrete. All<br />

important concrete shall be machine mixed to give complete coating of cement<br />

mortar on each coarse aggregate particle and to produce uniform coloured concrete<br />

with uniform distribution of materials. The mixer shall be run minimum<br />

1½ minutes. In case, for a minor job, hand mixing is permitted by the Engineer, it<br />

shall be done on smooth watertight platform not allowing the added water to flow<br />

out. The fine aggregate shall be spread in uniform thickness layer over which<br />

cement as required shall be placed and they shall be mixed thoroughly to give<br />

dry mortar.<br />

Water is then added gradually in required proportion, turning the mass, to give<br />

desired consistency mortar. The required quantity of coarse aggregate is then placed<br />

on mixing platform, wetted and mortar added. The entire mass is turned and<br />

returned to give uniform concrete of required consistency. 5% additional cement<br />

shall be used for hand mixed concrete.<br />

Admixtures: Any admixtures approved by the Engineer, which may be used, shall<br />

be measured separately in calibrated dispensers and shall be added to the mixture<br />

together with the water.<br />

GTS : General Technical Specification. Page 60