(<strong>II</strong>I) Coarse aggregate:<br />

a) Coarse aggregate for concrete, except as noted above, shall conform to<br />

IS: 383. This shall consist of crushed stone and shall be hard, strong,<br />

durable clean and free from elongated, flaky or laminated pieces,<br />

adhering coatings, clay lumps, coal residue, clinkers, slag, alkali,<br />

mica, organic matter or other deleterious matter.<br />

b) Screening and washing: Crushed rock shall be screened and or<br />

washed for the removal of dirt or dust coating, if so requested by the<br />

Engineer.<br />

c) Grading: Coarse aggregate shall be either in single size or graded, in<br />

both cases the grading shall be within the following limits.<br />

Percentage passing for single sized Percentage passing for graded<br />

IS Sieve aggregate of normal size aggregate of normal size<br />

Desig- nation 40 20 16 12.5 10 40 20 16 12.5<br />

mm mm mm mm mm mm mm mm mm<br />

63 mm 100 -- -- -- -- 100 -- -- --<br />

40 mm 85 100 -- -- -- 95 -- -- --<br />

100<br />

100<br />

20 mm 0 85 100 -- -- 30 95 100 --<br />

20 100<br />

70 100<br />

16 mm -- -- 85 100 -- -- -- 90 --<br />

100<br />

100<br />

12.5 mm -- -- -- 85 100 -- -- -- 90<br />

100<br />

100<br />

10 mm 0 0 0 0 85 10 25 30 40<br />

5 20 30 45 100 35 35 70 85<br />

d. Water: Water for mixing concrete, mortar or grout shall conform to<br />

IS:456-2000. If required to do so by the Engineer, the Contractor shall<br />

take samples of the water and test them for quality.<br />

7.3 Transporting and depositing concrete.<br />

Mixing plant shall be located as close as possible to the point of placement.<br />

Concrete shall be placed within 30 minutes after mixing and shall be transported<br />

from the mixer to its final placement as rapidly as practicable, taking care to see that<br />

no segregation or loss of ingredients take place. It shall also be ensured that the<br />

concrete is of the required workability at the point and time of placing.<br />

GTS : General Technical Specification. Page 52