5.9 Over excavation of trench bottom.<br />

All excavation carried below the grades shown on drawings or bottom of the<br />

bedding shall be refilled with sand/concrete at the Contractor's expense.<br />

5.10 Excavated material.<br />

The material from the excavation shall be deposited on either side of the trench<br />

leaving clear berm on one side at least 40cm wide or at such further distance from<br />

the edges of the trench as may be necessary to prevent the weight of materials from<br />

causing the side of the trench to slip or fall, or at such a distance and such a manner<br />

as to avoid any wall or structure or causing inconvenience to the public or other<br />

persons or otherwise as the Engineer may direct, till it is carted away.<br />

The excavated soil should be so placed and handled as not to inconvenience the<br />

usual traffic, till it is carted away. The Contractor should also provide necessary<br />

bridging over the excavated trenches for the house-holders and pedestrians to cross<br />

over and vehicular crossings if and where required at no extra cost; if the Engineer<br />

decides that there is no hindrance to traffic due to not carting away the excavated<br />

earth, he will give instructions to that effect. The Contractor shall be responsible for<br />

making all arrangements for the disposal of surplus excavated material upto a<br />

distance of 10kms.<br />

5.11 Pipe bedding.<br />

Sand Bedding: Where specified, the river sand bedding the required thickness and<br />

level shall be provided below pipe prior to laying the pipe in trenches. It shall be<br />

compacted with a light hand hammer. Any reduction in compaction shall be made<br />

up by adding sand during ramming. For the purpose of bedding under this item,<br />

only screened fine sand of grain size not larger than 2mm shall be used. The sand<br />

shall be clean, uncoated and free from clay lumps, injurious amount of dust, soft<br />

particles, organic matter, loam or other deleterious substances.<br />

If the sand supplied is unclean, it shall be washed. In no case shall sand containing<br />

more than 3.5% by dry volume or 5% by wet volume of clay, loam or silt be<br />

accepted. Tests specified for determining silt in sand and organic impurities<br />

described in IS: 383 shall apply. Sieved and washed sand shall be stored on the<br />

works in such a manner as to prevent intrusion of any foreign matter, including<br />

coarser particle of sand or any clay or metal or chips. Tests as indicated above shall<br />

be performed if called for by the Engineer at the expense of the Contractor.<br />

GTS : General Technical Specification. Page 36