5.1 Description.<br />

Chapter 5<br />

Earth Work<br />

The work specified in this section includes the provision of all labour, machinery,<br />

construction equipment and other appliances required to perform all earthwork<br />

specified or required, in a sound, workmanlike manner.<br />

5.2 General.<br />

Excavation shall be required to be done for the following works:<br />

a) Excavation for underground pipelines.<br />

b) Excavations for valve chambers, Thrust blocks and Special structure<br />

No separate payment shall be made for removal of shrubs, which are less than<br />

100mm in diameter at breast height, grass, small bushes and stumps. The alignment<br />

of the main shall be so fixed as to avoid cutting of any trees.<br />

No extra payment shall be made to the Contractor for working in a confined space.<br />

5.3 Classification.<br />

The excavation work shall be classified into the following categories by inspection<br />

of faces of cutting:<br />

i) Loamy, clayey soils like black cotton soils, red earth, hard gravel, mixture of gravel<br />

and soft disintegrated rock like shale, ordinary gravel, stony earth and earth mixed<br />

with fair sized boulders, except rock requiring blasting, chiseling, wedging etc.<br />

ii) Hard rock and boulders to be removed by benching, chipping, chiseling, wedging,<br />

barring and by controlled blasting wherever permissible.<br />

GTS : General Technical Specification. Page 33