Chapter 24<br />

Technical Specification for laying of Clear Water Rising Main<br />

24.1 Introduction.<br />

The clear water rising main shall consists of 300mm dia. DI pipes for a total length<br />

of 6570Rm. Water from the RCC clear water sump shall be pumped through a<br />

300mm dia. DI pipes to the proposed storage reservoir under Zone X<strong>II</strong>.<br />

24.2 Scope of work.<br />

Scope of work includes survey, layout, design, engineering and laying of clear<br />

water rising main of sizes 300mm for a total length 6570Rm from clear water<br />

pump house to the proposed storage reservoirs under zone X<strong>II</strong>. In laying of clear<br />

water rising main, DI pipes including all specials and fittings like bends, flanges,<br />

sluice valves, Air valves, tyton joints, rubber gasket, etc. and other accessories<br />

including Non-return valves and expansion joints shall be supplied by the<br />

department. Providing pipe supports and anchor block wherever is necessary is<br />

within the scope of the tender.<br />

Detailed design and drawings clearly showing the plan and L-Section of the clear<br />

water rising main indicating the location of valves, air valves and anchor block etc.<br />

including structural drawings of anchor block, valve chamber are required to be<br />

submitted. The work can be started only after the approval of the design & drawing<br />

by the engineer-in-charge.<br />

Taking delivery and transportation of pipes, valves, which are issued as per<br />

free issue of materials from the PHED Store at Mawphlang transporting them<br />

to work site and custody of the same till completion of erection and<br />

commissioning. The Contractor shall be responsible for proper accounting of these<br />

material and return the surplus material if any to PHED stores as per direction of<br />

Engineer-in-charge.<br />