The system may also demand for solo pump operation in varying level conditions of<br />

the sump and the pumps shall be suitable for solo as well as parallel operation for<br />

future requirement. The pump duty point shall be considered at the individual pump<br />

flow of the combined station flow by 2 pumps. However, the pumps shall be<br />

suitable for continuous operation both solo and 2 pumps in parallel mode.<br />

The RCC sump and pump house shall have a provision of installing 1 more<br />

horizontal split casing pump sets so as to feed the water to the storage reservoir. The<br />

rising main of 300mm dia. shall transport the water for the present and future<br />

demand. Thus in future, there shall be an additional pump set where 2 shall be in<br />

operation and working and 1 standby system to meet the future demand as stated<br />

above.<br />

23.2 Scope of Electro mechanical works.<br />

The Scope of Work covers selection, manufacture, testing at manufacturer’s works,<br />

supply and delivery to store at project site properly packed for transportation on<br />

F.O.R site basis, receiving at store and site including loading and unloading at all<br />

terminal points, safe storage, installation, pre-commissioning activities, trial run,<br />

commissioning, field testing, operation and maintenance for a period of 3 months of<br />

the plant with all associated equipments and ancillaries. All electro-mechanical<br />

components of the pump house including pumps, motor, starters, H.T./L.T. Panel<br />

boards, pipes, valves and specials, overhead crane and trolley etc. shall be under the<br />

scope of this tender. Both suction and delivery valves inside the pump house shall<br />

be butterfly valves with motorized actuator and position indicator. Arrangement of<br />

feeding H.T./L.T., 3 phase A.C. Power supply to the H.T./L.T. Panel Board in the<br />

Pump House shall not however be under the scope of this tender and the same shall<br />

be arranged separately by the employer/owner. Civil construction of the RCC sump<br />

& pump house including laying of the Rising Main for lifting the water into storage<br />

reservoir of Zone X<strong>II</strong> in which the pumps shall be installed and commissioned is<br />

detailed out elsewhere in this document. Motor and other associated equipments<br />

shall be compatible with VVVF drives including automation control and<br />

visualization system. VVF drives and PLC system is however outside the scope of<br />

this tender.<br />

It is the responsibility of <strong>Bid</strong>der to have thorough understanding of reference<br />

document, site condition and specifications. The intending <strong>Bid</strong>der shall be deemed<br />

to have visited the site, studied the condition, collected relevant and required data<br />

before submitting the bid to make the bid complete and correct in all respect. Nonfamiliarity<br />

with the site condition will not be considered a reason either for extra<br />

claim or for not carrying out the work in strict conformity with the<br />

specifications/acts/code of practices/rules and regulations of local Electrical<br />

inspectorate.<br />

<strong>Bid</strong>der shall be responsible and assist client in obtaining all statutory clearance as<br />

required from Statutory Authority.<br />

DTS : Detailed Tender Specification. Page 272