Chapter 22<br />

Technical specification for laying of Gravity Main and Feeder Main<br />

22.1 Introduction.<br />

The clear water gravity main and feeder main shall consists DI pipes of size ranging<br />

from 1000mm to 100mm which shall convey water from the water treatment plant<br />

to different zonal reservoirs for a total length of 58063Rm..<br />

22.2 Scope of work.<br />

Scope of work includes survey, layout, design, engineering and laying of clear<br />

water gravity main & feeder main DI pipelines of sizes 1000mm to 100mm for<br />

a total length 58063Rm from water treatment plant to different zonal reservoirs. The<br />

sizes and length of DI pipes covers under the contract are :<br />

1000mm - 2976 Rm<br />

900mm - 7724 Rm<br />

750mm - 2800 Rm<br />

300mm - 9530 Rm<br />

250mm - 12170 Rm<br />

200mm - 9047 Rm<br />

150mm - 13270 Rm<br />

100mm - 546 Rm<br />

In laying of the gravity main and feeder main, the requirement of DI pipes in<br />

random length of 4 to 7m will be supplied by the department from its Godown at<br />

Mawphlang including all specials and fittings like bends, flanges, expansion joints<br />

and valves viz. Sluice Valves for the main, sectionalizing and scouring of the line<br />

and also Air Valves, for fitting and fixing by the Contractor. Providing pipe<br />

supports and anchor block wherever is necessary is within the scope of the tender.<br />

Detailed design and drawings clearly showing the plan and L-Section of the gravity<br />

main indicating the location of valves, air valves and anchor block etc. including<br />

structural drawings of anchor block, valve chamber are required to be submitted.<br />

The work can be started only after the approval of the design & drawing by the<br />

engineer-in-charge.<br />

Taking delivery and transportation of pipes, valves, which are issued as per<br />

free issue of materials from the PHED Store at Mawphlang transporting them<br />

to work site and custody of the same till completion of erection and<br />

commissioning. The Contractor shall be responsible for proper accounting of these<br />

material and return the surplus material if any to PHED stores as per direction of<br />

Engineer-in-charge.<br />

DTS : Detailed Tender Specification. Page 257