21.29 Chemical house service water.<br />

The contractor shall arrange for pressure water supply to chemical house, by<br />

tapping the wash water line, that conveys pressure water for back wash filters from<br />

the elevated service reservoir in the same campus. This wash water line is to be<br />

supplied by the contractor and is included in the filtration works. Pipe work fittings<br />

etc. shall be provided by the contractor to ensure that adequate supplies are<br />

available for the works and the any two stock tanks can be filled with water within<br />

20 minutes.<br />

21.30 High pressure water.<br />

The contractor shall provided services pumps on the clear water channel and supply<br />

pressurized water to the chemical house and throughout the works at appropriate<br />

points to enable all external tanks, chambers chemical areas etc., to be hosed down<br />

and to enable all chemical dosing lines to be flushed when required.<br />

21.31 Waste disposal.<br />

The contractor shall arrange the works and shall made provision for the removal of<br />

all waste products, from the site to the mud well situated in the same campus and<br />

functioning to collect by gravity' and dispose off by pumping all the waste products<br />

from the existing treatment plant to a surface stream. Waste shall be removed from<br />

site in an open or closed conduit. Waste disposal shall be by gravity. Particular<br />

attention shall be paid to facilitate cleaning of alum tanks, channels etc. However, if<br />

levels do not permit, only then pumping may be adopted.<br />

21.32 Inter connecting pipe work and drains.<br />

The contractor shall provide the interconnecting pipe work required in the works to<br />

provide a complete operation. He shall include in his offer the waste water<br />

discharge main connected with all the branches provided to collect and dispose the<br />

waste products from the works to the Nala. Tendering contractors shall specify the<br />

rates of flow, diameters and levels of all drains leading from any part of the works<br />

arranged by them in order to suit their own design. These details together with<br />

complete calculations shall be included in the tender submission. The contractor<br />

shall indicate at the time of tendering the location and required capacity of all<br />

drainage points which he required for the satisfactory operation of the works. The<br />

complete drainage requirement shall be finalized by the contractor with in 4 months<br />

of the date of acceptance of the tender. Contractor can choose the piping material as<br />

per requirement.<br />

DTS : Detailed Tender Specification. Page 256