21.3 Intent and requirement.<br />

The intent of the tender is survey, design, engineering and construction of water<br />

treatment plant to augment the capacity of existing WTP.<br />

Present phase and future requirement :<br />

The shortfall in the supply for the intermediate and ultimate stage of the project is<br />

8 MLD and 24 MLD respectively. Considering the high turbidity of water during of<br />

monsoon months, leading to the over-loading of the clari-flocculator of 34.05 MLD<br />

WTP, it is proposed to construct clari-flocculator identical in size and shape and<br />

having same level of construction as that of the clari-flocculator of existing<br />

34.05 MLD water treatment plant. The incoming raw water from existing rising<br />

main and proposed rising main (34.05+8MLD) shall be shared by<br />

2 clarri-flocculator @ 42.05/2 i.e. 21.025 MLD thereby reducing the load of the<br />

existing clari-floculator. The clarified/settled water from both the clarifier shall be<br />

shared by both the filtration plant by interconnecting the clarified/settled water<br />

channel of both the clari-flocculator. The filter house and associated plant shall be<br />

constructed to yield 8 MLD of water and with provision for future expansion of the<br />

plant to yield 24 MLD to meet the shortfall for the ultimate stage.<br />

21.4 Scope of work.<br />

The scope of work covers survey, design, engineering and construction of civil<br />

work components of the WTP, including selection, manufacture, supply and<br />

delivery to store at project site of electro-mechanical equipments and<br />

instrumentations properly packed for transportation in F.O.R. site basis, received at<br />

store and site including loading and unloading at all terminal routes, safe storage,<br />

installation, pre-commissioning activities, trial run, commissioning, field testing<br />

operation and maintenance for a period of 3 months of the plant with all accessories<br />

and ancillaries. The associated plant and equipments to be installed shall be<br />

compatible with automation control and visualization system provided with<br />

centrally controlled and monitoring system. Automation control and visualization<br />

system is however outside the scope of this tender.<br />

It is the responsibility of <strong>Bid</strong>der to have thorough understanding of reference<br />

document, site condition and specifications. The intending <strong>Bid</strong>der shall be deemed<br />

to have visited the site, studied the condition, collected relevant and required data<br />

before submitting the bid to make the bid complete and correct in all respect. Nonfamiliarity<br />

with the site condition will not be considered a reason either for extra<br />

claim or for not carrying out the work in strict conformity with the<br />

specifications/acts/code of practices/rules and regulations of local Electrical<br />

inspectorate.<br />

DTS : Detailed Tender Specification. Page 238