In the design selection of pumping machineries for Intermediate pumping station,<br />

the following conditions are to be taken into consideration.<br />

The datas given above with reference to RL are indicative and are not to be<br />

considered as final. After finalisation of tender, if any change in the site, RL s,<br />

resulting in change of operating head of the pumps, the contractor should arrange<br />

design & selection of pumping plant/machineries for approval by the department<br />

before proceeding for order of the same. The contractor are required to visit the site,<br />

conduct survey, collect necessary datas required in designing and selection of<br />

suitable pumping plant/machineries. The detail design calculation including<br />

selection of type of pumps, motor, motor control center including type of starters,<br />

cabling and valves inside the pump house viz. Sluice/butterfly valves and Nonreturn<br />

valves are to be furnished along with the tender.<br />

Though the wall thickness of the pipes for rising main may be sufficient to<br />

withstand very severe surge pressure, the valves in the pump house including the<br />

delivery manifold is required to be properly selected so as to prevent the damage of<br />

the machineries in the event of sudden tripping of pumps as a result of power<br />

failure. In the case of intermediate pumping station, the picture is comparatively<br />

worsen as the total head is comparatively higher. In such a situation, water<br />

hammering would be quite severe in the event of power failure. Considering the<br />

total pump head, the valves inside the pump house including the delivery manifold<br />

should have a working pressure of not less than 1.5 times the working pressure. Non<br />

return valves on the individual pump delivery lines are proposed to be provided<br />

with dash pot arrangement to dampen the rate of closure towards the end of closure.<br />

Air valves are to be provided in the rising main.<br />

Technical specification of the horizontal split casing pump.<br />

Codes and Standards : Has been detailed elsewhere in this document.<br />

Design and Performance Requirement : Has been detailed elsewhere in this<br />

document.<br />

Drawing, data, curves and manuals : Has been detailed elsewhere in this<br />

document.<br />

Materials of construction : Has been detailed elsewhere in this document.<br />

Inspection and Testing : Has been detailed elsewhere in this document.<br />

Packing for Transportation : Has been detailed elsewhere in this document.<br />

DTS : Detailed Tender Specification. Page 227