The different levels in the proposed RCC Sump at intermediate stage pumping<br />
station and the water treatment plant have been indicated in the document based on<br />
which the <strong>Bid</strong>der shall calculate the pump working heads at different conditions. To<br />
calculate the frictional head loss in straight pipe, Hazen William’s formula taking<br />
‘C’ value as 100 shall be considered. In order to estimate the frictional head loss for<br />
bends, curves, valves, specials etc. in the Raw Water rising Main an increment of<br />
20% on the calculated frictional head loss of the rising main shall be considered.<br />
The system may also demand for solo pump operation in varying level conditions of<br />
the sump and the pumps shall be suitable for solo as well as parallel operation. The<br />
pump duty point shall be considered at the individual pump flow of the combined<br />
station flow by 2 pumps. However, the pumps shall be suitable for continuous<br />
operation both solo and 2 pumps in parallel mode.<br />
The RCC sump and pump house shall have a provision of installing 3 more<br />
horizontal split casing pump sets so as to feed the raw water to the additional Water<br />
Treatment Plant to be constructed adjacent to the present one. The existing rising<br />
main of 500mm dia. shall transport the raw water in the present and future demand.<br />
Thus in future, there shall be an additional pump battery of 3 pump sets having<br />
2 working and 1 standby system to meet both for the present and future demand as<br />
stated above.<br />
20.2 Scope of electro-mechanical works.<br />
The Scope of Work covers selection, manufacture, testing at manufacturer’s works,<br />
supply and delivery to store at project site properly packed for transportation on<br />
F.O.R site basis, receiving at store and site including loading and unloading at all<br />
terminal points, safe storage, installation, pre-commissioning activities, trial run,<br />
commissioning, field testing, operation and maintenance for a period of 3 months of<br />
the plant with all associated equipments and ancillaries. All electro-mechanical<br />
components of the pump house including pumps, motor, starters, H.T./L.T. Panel<br />
boards, pipes, valves and specials, overhead crane and trolley etc. shall be under the<br />
scope of this tender. Both suction and delivery valves inside the pump house shall<br />
be butterfly valves with motorized actuator and position indicator. Arrangement of<br />
feeding H.T./L.T., 3 phase A.C. Power supply to the H.T./L.T. Panel Board in the<br />
Pump House shall not however be under the scope of this tender and the same shall<br />
be arranged separately by the employer/owner. Pumps, motors and other associated<br />
equipments shall be compatible with VVVF drives including automation control<br />
and visualization system. VVVF drives and PLC system is however outside the<br />
scope of this tender.<br />
DTS : Detailed Tender Specification. Page 224