Foundation & Civil Works :<br />

Equipment foundations panel foundations and all other civil work will be provided by<br />

the Contractor.<br />

Excavation and Back Filling :<br />

The Contractor shall perform all excavation and backfilling as required for buried<br />

cable and ground connections.<br />

Excavation shall be performed up to the required depth. The Contractor shall make<br />

use of his own arrangements for pumping out any water that may be accumulated in<br />

the excavation. All excavation shall be backfilled to the original level with good<br />

consolidation.<br />

Steel Fabrication :<br />

All supports, hangers & brackets shall be fabricated by the Contractor. Necessary<br />

steel shall be supplied by the Contractor. Steel for fabrication shall be straightened<br />

and cleaned of rust and grease.<br />

Painting at site.<br />

Street light poles shall be given two coats of aluminium paints after installation.<br />

All steel fabrication shall be given two coats of red oxide primer followed by two<br />

coats of battleship grey shade.<br />

All equipment shall be given touch-up paint as required after installation.<br />

Testing of installation :<br />

The Contractor will provide such checking and testing equipment as test lamp,<br />

buzzer, 500 volt meggar, earth megar, lux-meter etc. free of cost for maintenance<br />

purpose.<br />

DTS : Detailed Tender Specification. Page 219