For long run, junction/pull boxes shall be provided at suitable intervals to facilitate<br />

wiring. Conduits shall be securely fastened to junction box or cabinets, each with a<br />

locknut and insulated bushing inside the box and locknut outside. Conduit joints and<br />

connections shall be made thoroughly water-tight and rust-proof by application of a<br />

thread compound, which will not insulate the joints. The entire metallic conduit<br />

system, whether embedded or exposed, shall be electrically continuous and<br />

thoroughly grounded.<br />

Lighting fixture shall not be suspended directly from junction box in the main conduit<br />

run. Conduits and fittings shall be properly protected during construction period<br />

against mechanical injury. Conduits ends shall be plugged or capped to prevent entry<br />

of foreign material.<br />

In control rooms and office areas provided with false ceiling conduct run shall be<br />

concealed type, embedded in the walls.<br />

Wiring :<br />

Wiring shall be generally carried out by PVC wires in conduits. All wires in a conduit<br />

shall be drawn simultaneously. No subsequent drawing is permissible. Wire shall not<br />

be pulled through more than two equivalent 90` bends in a single conduit run. Wiring<br />

shall be spliced only at junction boxes with approved type connections or terminal<br />

strips. Maximum two wires can be connected to each way of the terminal block.<br />

Splicing of only one phase shall be done in a junction box.<br />

For lighting fixtures, connection shall be teed off through suitable round conduit or<br />

junction box, so that the connection can be attended without taking down the fixture.<br />

For vertical run of wires in conduit, wires shall be suitably supported by means of<br />

wooden/hard rubber plugs at each pull/ junction box. A.C. and D.C. circuits shall not<br />

be run in the same conduit and junction boxes. Receptacle circuits shall be kept<br />

separate and distinct from lighting and fan circuits.<br />

Separate neutral wire shall be provided for each circuit. Wiring throughout the<br />

installation shall be such that there is no break in the neutral wire in form of switch or<br />

fuse.<br />

DTS : Detailed Tender Specification. Page 217