19.14 Starters :<br />

In selection of starters for starting of electric motors, the following criteria are to be<br />

considered:<br />

1) The necessity to help in ensuring stability of the grid by reducing the starting KVA<br />

significantly.<br />

2) The necessity to improve the mechanical performance of the pump and the motor<br />

by providing smooth and jerkless starting.<br />

3) The necessity to Increase motor life by reducing the motor inrush current to a large<br />

extent.<br />

4) In vertical turbine pump with long suspension length, Direct Online start with very<br />

quick acceleration should be avoided. For longer life of the pumps, bearings and<br />

wearing rings the necessity for smooth jerkless starting is always desirable<br />

5) The necessity to improve the thermal characteristics thereby increasing the number<br />

of Start and Stop.<br />

6) The necessity to reduce the transformer rating and consequently the Transformer<br />

installed capacity by reducing the starting KVA.<br />

The <strong>Bid</strong>ders in their technical offer shall submit details of H.T/L.T Panel and MCC.<br />

19.15 Instrumentation and Control System.<br />

All instruments and Control System, Transmitters, Gauges, LCP, Annunciation<br />

System, Temperature Sensor/Scanner etc. along with all other accessories as<br />

required shall be provided to achieve desired control and monitoring functions of<br />

the station.<br />

Following field instruments shall be provided for necessary indication, interlock,<br />

monitoring purposes as a general guideline. The Contractor shall provide all<br />

necessary instruments for safe and efficient operations of the Plant: -<br />

(a) Level Control System for each Pump;<br />

(b) Level indication arrangements for the common Intake Well;<br />

(c) Pressure gauge for each Pump discharge and Pump common header;<br />

(d) Pressure transmitter for the Pump Common Header;<br />

(e) Pump Common Header Pressure Switch for low pressure indication and alarm;<br />

(f) RTD for Motor winding, Bearing temperature for Pump and Motor;<br />

DTS : Detailed Tender Specification. Page 199