The different levels in the reservoir well and the proposed RCC Sump at<br />

intermediate stage pumping station have been indicated in the document based on<br />

which the <strong>Bid</strong>der shall calculate the pump working heads at different conditions. To<br />

calculate the frictional head loss in straight pipe, Hazen William’s formula taking<br />

‘C’ value as 100 shall be considered. In order to estimate the frictional head loss for<br />

bends, curves, valves, specials etc. in the Raw Water rising Main an increment of<br />

20% on the calculated frictional head loss of the rising main shall be considered.<br />

The system may also demand for solo pump operation in varying level conditions of<br />

the reservoir and the pumps shall be suitable for solo as well as parallel operation.<br />

The pump duty point shall be considered at the individual pump flow of the<br />

combined station flow by 2 pumps working at lowest water level 1562.00m of the<br />

reservoir which shall lie at 0.5m above the C/L of inlet port to be fixed at<br />

1562.50m. However the pumps shall be suitable for continuous operation both solo<br />

and 2 pumps in parallel mode at the above LWL condition and maximum HWL<br />

condition of the reservoir at 1577m and in between.<br />

The intake well cum pump house shall have a provision of installing 3 more vertical<br />

pump sets so as to feed the raw water to the additional Water Treatment Plant to be<br />

constructed adjacent to the present one. The existing rising main of 500mm dia.<br />

shall transport the raw water in the present and future demand. Thus in future, there<br />

shall be an additional pump battery of 3 pump sets having 2 working and 1<br />

standby system to take feed of raw water from the proposed single intake well to<br />

meet both for the present and future demand as stated above.<br />

19.2 Scope of electro-mechanical works.<br />

The Scope of Work covers selection, manufacture, testing at manufacturer’s works,<br />

supply and delivery to store at project site properly packed for transportation on<br />

F.O.R site basis, receiving at store and site including loading and unloading at all<br />

terminal points, safe storage, installation, pre-commissioning activities, trial run,<br />

commissioning, field testing, operation and maintenance for a period of 3 months of<br />

the plant with all associated equipments and ancillaries. All electro-mechanical<br />

components of the pump house including pumps, motor, starters, H.T./L.T. Panel<br />

boards, pipes, valves and specials, overhead crane and trolley etc. shall be under the<br />

scope of this tender. Both suction and delivery valves inside the pump house shall<br />

be butterfly valves with motorized actuator and position indicator. Arrangement of<br />

feeding H.T./L.T., 3 phase A.C. Power supply to the H.T./L.T. Panel Board in the<br />

Pump House shall not however be under the scope of this tender and the same shall<br />

be arranged separately by the employer/owner. Civil construction of the intake well,<br />

pump house and gangway over the reservoir from the bank to the pump house<br />

DTS : Detailed Tender Specification. Page 182