Chapter 19<br />

Technical specification for electro-mechanical plants,<br />

equipments and accessories for Raw water Intake pumping<br />

station.<br />

19.1 Intent and Requirement.<br />

Intent :<br />

The intent of the tender is to select, manufacture, testing at Manufacturers’ works,<br />

supply and delivery in duly packed condition F.O.R project site, installation,<br />

commissioning of vertical wet pit type pumping sets with accessories to be mounted<br />

on the Raw Water Intake Well and Gangway along with other equipments, field<br />

testing, operation and maintenance etc. as per the technical specification and other<br />

terms and conditions. The vertical wet pit type Raw Water pumping sets will serve<br />

as the intake pumps of the 8 MLD water treatment plant of GSWSP Phase <strong>II</strong>I.<br />

Source and Pump House :<br />

The source of water shall be Umiew Dam reservoir of Greater Shillong Water<br />

Supply Scheme, Intake well cum Pump house is proposed to be constructed at the<br />

reservoir bed in the identified location at some distance from the bank. Vertical<br />

pump sets shall be installed in the intake well of R.C.C. construction within the<br />

water body of the reservoir, mounting the same on the floor of the Intake well cum<br />

Pump House connected through a gangway of 4m width to be constructed from the<br />

bank. Under the scope of this tender the electrical control switches H.T/L.T. Board,<br />

indication and metering, instrumentation etc. shall be housed in the Pump House to<br />

be constructed for the purpose.<br />

Present Phase and Future Phase Requirement :<br />

There shall be total 3 nos. vertical wet pit pumps of identical type for the present<br />

phase and the same shall be operated as two pumps in parallel conditions of any<br />

combination and shall deliver the station flow of 8 MLD in 20 Hrs. of operation by<br />

2 pumps. Raw water shall be transported from the intake pumping station to the<br />

intermediate stage pumping station through a requisite size MS rising main pipe<br />

having approximate length of 750Rm.<br />

DTS : Detailed Tender Specification. Page 181