(b) Pressurization : Each valved section of pipe shall be filled with water slowly and the<br />

specified test pressure, based on the elevation of lowest point of the linear section<br />

under test and corrected to the elevation of the test gauge, shall be applied by means of<br />

a pump connected to the pipe in manner satisfactory to the Engineer-in-charge.<br />

(c) Examination under pressure : Under the test pressure no leak or sweating shall be<br />

visible at all section of pipes, fittings, valves, hydrants and welded joints. Any<br />

defective pipes, fittings, valves or hydrants discovered in consequence of this pressure<br />

test shall be removed and replaced by sound materials and the test shall be repeated<br />

until satisfactory to the Engineer-in-charge.<br />

18.11 Wrapping & Coatings.<br />

The wrapping and coating for buried portion of pipeline shall be as per AWWA-C-<br />

203 and as indicated below.<br />

One coat of Shalimar/eq. plasticized coal tar primer cold application.<br />

A hot flood coat of plasticized coal tar with inner wrap at fiber glass resin polyester<br />

tissue followed by a second flood coat of hot coating of plasticized coal tar with outer<br />

wrap of fiber glass resin polyester tissue.<br />

The total thickness of both coating will not be less than 4.5 mm.<br />

Alternately protective coating and wrapping by tapes as per IS 10221 tapping shall<br />

be provided. Total thickness shall not be less than 4 mm, number of layers shall be<br />

minimum 7, thickness of centre cone in microns shall be 90, material of tape<br />

polyester reinforcement, softening point not less than 90 deg, penetration minimum<br />

4mm, pliability 5 deg, tensile strength not less than 160 N/sq. cm, test certificate for<br />

the tapes as per relevant codes shall be furnished.<br />

Where the pipe line is partly above ground and partly underground, the coating use on<br />

the buried portion should be continued well clear of the ground.<br />

Internal painting – The inside of the pipes should be protected against corrosion by the<br />

use of internal painting.<br />

18.12 Flushing and disinfection of mains before commissioning:<br />

The mains intended for potable water supplied should be disinfected before<br />

commissioning them for use.<br />

Distribution system chlorination of new mains : Special care should be taken to ensure<br />

disinfection of new mains. Among possible sources of contamination are sewer<br />

drainage, contaminated soil in the trench, contamination from workmen or their<br />

equipment or both and unavoidable foreign material present in the trench during<br />

construction.<br />

DTS : Detailed Tender Specification. Page 176