Cable Accessories:<br />

All accessories like cable glands, lugs and terminal markings etc. shall be used<br />

conforming to relevant standards / as specified. For 1100V grade cables Siemens<br />

type gland and crimping type lugs shall be used.<br />

Cable Laying:<br />

The power cables and its accessories shall confirm to latest relevant Indian<br />

Standards. While laying the cables care shall be taken to avoid formation of kinks<br />

and damages to the cables.<br />

LT cable shall be laid on wall with suitable clapping or trays or buried underground<br />

with appropriate protection. Black shall indicate the neutral, while red, yellow and<br />

blue for three different phases. All LT cables when laid on the cable racks shall be<br />

properly dressed and clamped as required without crisscrossing and unnecessary<br />

overlapping. Cables shall be properly dressed and clamped.<br />

Laying of LT under ground cables :<br />

The laying of UG cables on ground is by excavating a trench of 0.75 meter depth<br />

for LT cable. Before the cable is laid in the trench, the bottom of the trench shall be<br />

cleared from stones and other sharp materials and filled with sand layer of 150 mm.<br />

The width of the trench at bottom shall be 0.4 meters for one cable. In case the total<br />

number of cables laid in trenches is more than one, then the width shall be such that<br />

the spacing between cables is not less than 150 mm. Each run of cable shall be<br />

protected by placing bricks/RCC slabs on both the sides and top.<br />

After placing bricks or RCC slabs, the trench shall be filled with the excavated soil,<br />

in layers ensuring that each layer is well rammed by spraying water and<br />

consolidated. The extra earth shall be removed from the trench and disposed as<br />

directed.<br />

When cables pass through roads they must be well protected by either hume pipes<br />

or GI pipes of suitable dimensions properly sealed at either end and also at the<br />

joints with suitable compound to avoid entry of soil and water.<br />

GTS : General Technical Specification. Page 116