13.08.2013 Views

Mining_Methods_UnderGround_Mining - Mining and Blasting

Mining_Methods_UnderGround_Mining - Mining and Blasting

Mining_Methods_UnderGround_Mining - Mining and Blasting

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Plan of pre-undercut holes.<br />

el TenienTe, CHile<br />

the undercut level difficult. The effective<br />

extraction rate defined for the Es-<br />

meralda sector was 0.14 to 0.44 t/day/<br />

sq m at the initial caving stage, <strong>and</strong><br />

reached 0.28 to 0.65 t/day/sq m at the<br />

steady-state caving stage. The height<br />

of primary ore column to be exploited<br />

is around 150 m, relatively low if compared<br />

with Teniente 4 Sur, where the<br />

height is over 240 m.<br />

At Esmeralda, 7 cu yd LHDs working<br />

on the production level load <strong>and</strong> tip<br />

into 3.5 m-diameter ore passes. Here,<br />

teleremote controlled hydraulic breakers<br />

positioned above 1 m x 1 m grizzlies<br />

break any oversize rock before it goes<br />

Drilling patterns in <strong>and</strong>esite <strong>and</strong> breccia.<br />

St<strong>and</strong>ard drill plan with 4 hole-fans<br />

through the ore pass <strong>and</strong> into the loading<br />

bin. On the haulage level, the<br />

mineral is loaded into trains featuring<br />

Automatic Train Protection (ATP) <strong>and</strong><br />

consisting of a locomotive with eight 50<br />

t cars. These trains, which were retrofitted<br />

with an Automatic Train Operation<br />

(ATO) system, tip into storage bins<br />

which feed a 5.0 m-diameter orepass<br />

to the main transport level Teniente 8.<br />

Trains with 90 t electric locomotives<br />

<strong>and</strong> 18 cars each of 80 t capacity carry<br />

the mineral out to the Colón concentrator.<br />

The main haulage level at Teniente<br />

8 was recently upgraded, incorporating<br />

new technology similar to Esmeralda.<br />

HW FW HW<br />

FW<br />

Drill plan with 3 x 3 hole-fans Drill plan with 4 x 4 hole-fans<br />

HW FW HW<br />

FW<br />

Basic concepts<br />

In the conventional panel caving <strong>and</strong> the<br />

pre-undercut variant, the same basic con-<br />

cepts apply. The main difference is the<br />

sequence of each of the operational ele-<br />

ments. In the conventional panel caving<br />

method, the sequence of activities is:<br />

development of tunnels on each level<br />

for production <strong>and</strong> undercut; drawbell<br />

opening; undercut blasting; <strong>and</strong> extraction.<br />

In the pre-undercut variant, the un-<br />

dercut is excavated first, <strong>and</strong> the production<br />

level is developed subsequently<br />

within the stress-relieved zone: development<br />

of the undercut level; undercut<br />

blasting; development of the production<br />

level; drawbell opening; <strong>and</strong> extraction.<br />

The main challenge associated with<br />

this variant involved the undercutting.<br />

Several alternatives were tried, with<br />

the current preference being a flat, low<br />

height 3.6 m undercut. The undercut is<br />

blasted some 80 m ahead of the actual<br />

production zone, with the production<br />

level <strong>and</strong> drawbell development following<br />

around 22.5 m behind the undercut,<br />

<strong>and</strong> 57.5 m ahead of the production<br />

zone.<br />

The undercut comprises drives, 3.6<br />

m-wide by 3.6 m-high, developed parallel<br />

to each other on 15 m centres. The<br />

excavation of the undercut is achieved by<br />

blasting three- or four-hole fans, some<br />

7 m to 10 m length, drilled into the sidewall.<br />

The drill holes are fanned slightly,<br />

to ensure an undercut height equal to<br />

the height of the drives. Swell material<br />

from each undercut blast is removed by<br />

LHD to provide a free face for the next<br />

blast. The production haulage level is<br />

developed 18 m below the undercut,<br />

giving a crown pillar thickness of 14.4<br />

m through which the drawbells are then<br />

developed straight into the pre-blasted<br />

undercut. The production level requires<br />

substantial support, with fully grouted<br />

2.3 m rebar installed in a 0.9 m x 1.0<br />

m pattern immediately behind the face,<br />

followed by chain mesh <strong>and</strong> shotcrete.<br />

Permanent support is added around 15 m<br />

behind the face, <strong>and</strong> consists of fully<br />

grouted long cable bolts, with additional<br />

reinforcement at drawpoints. One of the<br />

challenges of this method is that two<br />

mining fronts have to be managed, one<br />

on the undercut level, <strong>and</strong> the other located<br />

on the production level, <strong>and</strong> these<br />

86 underground mining methods

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!