13.08.2013 Views

Mining_Methods_UnderGround_Mining - Mining and Blasting

Mining_Methods_UnderGround_Mining - Mining and Blasting

Mining_Methods_UnderGround_Mining - Mining and Blasting

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

caving in primary rock. Currently, two<br />

forms of panel caving are in use: stan-<br />

dard panel caving as applied in the<br />

Teniente 4 Sur Sector; <strong>and</strong> panel<br />

caving with pre-undercut as used in the<br />

Esmeralda Sector.<br />

exploitation sequence<br />

The panel caving exploitation sequence<br />

initially used involved development<br />

<strong>and</strong> construction of production levels,<br />

undercutting at the undercut level, <strong>and</strong><br />

ore extraction. However, the dynamic<br />

caving fronts, under high stress conditions<br />

of 40-60 Mpa, resulted in substantial<br />

damage to the infrastructure.<br />

Indeed, extraction in El Teniente Sub<br />

6 Sector had to be stopped in March,<br />

1992 after several rockbursts caused<br />

fatal accidents, reflecting the low level<br />

of knowledge at the time about mining<br />

in primary rock.<br />

Between June, 1994 <strong>and</strong> August, 1997,<br />

El Teniente carried out experimental<br />

mining in a pilot area of 12,000 sq m.<br />

This process was closely monitored, <strong>and</strong><br />

the data served as the basis for a full<br />

geomechanical study. From September,<br />

1997 to June, 1998, during the preoperational<br />

phase, it was realized that<br />

it was necessary to research the relationship<br />

between seismic potential,<br />

undercutting speed <strong>and</strong> the mining of<br />

new areas. Because of this, <strong>and</strong> for the<br />

first time since the 1992 production<br />

freeze, El Teniente carried out preparatory<br />

work in a 6,000 sq m area using<br />

simultaneous production techniques.<br />

The test succeeded, with no significant<br />

rockbursts, thus proving the relationship<br />

between seismicity <strong>and</strong> caving<br />

speed. Indeed, it is now recognized that<br />

the uncontrolled seismicity induced by<br />

the mining extraction rate of advance<br />

of the caving face <strong>and</strong> extraction speed<br />

has been the main cause of damage to<br />

the tunnels <strong>and</strong> infrastructure on the<br />

lower levels.<br />

Nowadays, there are variables incorporated<br />

into the mining design <strong>and</strong> planning<br />

concept to control the excess of<br />

seismic activity, not only improving the<br />

working conditions on the production<br />

level, but also increasing productivity.<br />

During the pre-operational phase, over<br />

2 million t were removed from Teniente<br />

Sub 6, with only two small rockbursts.<br />

Panel caving with pre-undercut at Esmeralda.<br />

esmeralda pre-undercut<br />

Following on from the studies <strong>and</strong> controlled<br />

tests, El Teniente introduced a<br />

variation of its conventional panel caving<br />

undercut sequence. Known as<br />

pre-undercut, it essentially consists of<br />

developing the production level behind<br />

the undercut, rather than the more<br />

typical method where the production<br />

development is carried in parallel with<br />

the undercut ahead of the caving face.<br />

The pre-undercut achieves a better redistribution<br />

of the stresses ahead of the<br />

production development, resulting in<br />

less damage <strong>and</strong> improved safety.<br />

Although the pre-undercut variant<br />

had been tested in some small sectors of<br />

the mine, it was first used on an industrial<br />

scale in the new Esmeralda sector.<br />

Occupying a total area of 714,000 sq<br />

m, Esmeralda is located at 2,210 m asl<br />

within the El Teniente deposit, bounded<br />

el TenienTe, CHile<br />

on the west by the Braden breccia pipe,<br />

<strong>and</strong> in the north by El Teniente Sub 6<br />

Sector, <strong>and</strong> is below the Teniente 4 Sur<br />

Sector. Lithologically, it occurs mainly<br />

in <strong>and</strong>esite, <strong>and</strong> contains a total mineral<br />

reserve of 365 million t, with an average<br />

grade of 1.01% of copper <strong>and</strong> 0.024%<br />

of molybdenum. The total investment<br />

for Esmeralda was US$205.6 million,<br />

with conceptual engineering <strong>and</strong> design<br />

initiated in 1992, <strong>and</strong> caving starting in<br />

August, 1996. Ore production started in<br />

September, 1997, <strong>and</strong> has built up from<br />

an average of 4,000 t/day in 1998 to<br />

19,500 t/day in 2001, <strong>and</strong> full production<br />

of 45,000 t/day from 2005.<br />

Caving at Esmeralda was achieved<br />

with 16,800 sq m of available production<br />

undercut, once a problem of 'support<br />

points' was solved. These formed<br />

above the apex of the crown pillar, <strong>and</strong><br />

reduced the interaction between draw-<br />

points, making the flow of ore from<br />

underground mining methods 85

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!