„Danfoss”, heat cost allocators - DBDH
„Danfoss”, heat cost allocators - DBDH
„Danfoss”, heat cost allocators - DBDH
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
“Energy Efficient House” project<br />
in Basmanny District<br />
• Address: Denisovski lane, 22<br />
Type of house: new-built brick/monolith<br />
Number of apartments: 38. Most of the<br />
dwellers are subsidiants, moved from<br />
old emergency houses<br />
Heating system: two-pipe, vertical.<br />
Automatic <strong>heat</strong>ing substation, balancing<br />
valves and TRVs “Danfoss” installed<br />
according to the design project<br />
Additional equipment: radiator <strong>heat</strong> <strong>cost</strong><br />
<strong>allocators</strong> installed at the expense of DEZ<br />
Basmanny