Q2: Choose the most appropri<strong>at</strong>e answer and mark your answer <strong>on</strong> this paper.<br />
1. If our producti<strong>on</strong> schedule was set to be a chase str<strong>at</strong>egy with the weekly demand <strong>of</strong> Week 1: 5000; Week<br />
2: 3000; Week 3: 6000; Week 4: 4000. <strong>The</strong> regular capacity is 4000 per week. Wh<strong>at</strong> is the regular time<br />
producti<strong>on</strong> schedule per week in weeks 1 to 4?<br />
(a) 5000, 3000, 6000, 4000<br />
(b) 4000, 3000, 4000, 4000<br />
(c) 3000, 3000, 3000, 3000<br />
(d) 4000, 4000, 4000, 4000<br />
(e) N<strong>on</strong>e <strong>of</strong> the above<br />
B Steven Yee<br />
2. A process th<strong>at</strong> is high volume, extremely standardized, very low cost, but not very flexible is an example <strong>of</strong>:<br />
(a) Job Shop<br />
(b) C<strong>on</strong>tinuous Processing<br />
(c) B<strong>at</strong>ch Processing<br />
(d) Assembly Line<br />
(e) Project<br />
B Ashley Heis<br />
3. In most cases, the fastest way to increase capacity to meet a short-term requirement is to:<br />
(a) hire additi<strong>on</strong>al workers<br />
(b) subc<strong>on</strong>tract work<br />
(c) acquire more equipment<br />
(d) use overtime<br />
(e) outsource<br />
D Yao-D<strong>on</strong> Hung<br />
4. Gary opened an <strong>of</strong>fice accessory store to supply cartridges <strong>of</strong> copy machines to UTD SOM which uses 8<br />
cartridges a m<strong>on</strong>th. Gary charges $50 for a cartridge and $100 for a delivery. A SOM pr<strong>of</strong>essor figured out<br />
th<strong>at</strong> the holding cost <strong>of</strong> a cartridge is $8 per year. How many times in a year does SOM order cartridges<br />
from Gary?<br />
(a) less than <strong>on</strong>ce<br />
(b) <strong>on</strong>ce or more but less than twice<br />
(c) twice or more but less than thrice<br />
(d) thrice or more but less than four times<br />
(e) four times or more<br />
B, EOQ=48.9, Demand/EOQ=96/48.9, between 1 and 2, Gary Li<br />
5. M<strong>at</strong>tel just received an unexpected high-priority order for 150 Cabbage P<strong>at</strong>ch dolls th<strong>at</strong> must be shipped<br />
out as so<strong>on</strong> as possible. At this point there are no dolls in the assembly line. <strong>The</strong>re are six different st<strong>at</strong>i<strong>on</strong>s<br />
th<strong>at</strong> the dolls move through to be produced. Activity 1 takes 3 minutes, Activity 2 = 5 minutes, Activity 3<br />
= 2 minutes, Activity 4 = 3 minutes, Activity 5 = 5 minutes, Activity 6 = 4 minutes. How l<strong>on</strong>g will it take<br />
for M<strong>at</strong>tel to have the order ready for shipping?