15(A) (i)<br />

On failure to pay the service charges within stipulated period for the year then<br />

service charges shall be paid at higher rate by 10% alongwith interest to be<br />

computed from 61st day <strong>of</strong> the allotment in case <strong>of</strong> new allotments and from<br />

1st August <strong>of</strong> the year for old allottees.<br />

15(A) (ii) In cases <strong>of</strong> plots allotted for industrial, commercial or other purposes through<br />

auction, service charges shall be levied from the date <strong>of</strong> plot possession and<br />

shall be paid within 60 days from the date <strong>of</strong> possession for the year <strong>of</strong><br />

possession. If the plot possession is not taken within 90 days from the date <strong>of</strong><br />

100% development charges paid then the possession shall deemed to have<br />

been taken on 91st day <strong>of</strong> the payment <strong>of</strong> development charges for the<br />

purpose. Service charges for the year <strong>of</strong> allotment shall be charged<br />

proportionally for remaining period <strong>of</strong> the year from the month <strong>of</strong> allotment /<br />

possession as the case may be.<br />

(Substituted as per decision taken by IDC vide item 11 <strong>of</strong> the meeting held on 3.6.2000.)<br />

15(A)(iii). One time payment <strong>of</strong> service charges (for a block <strong>of</strong> 10 years):<br />

Allottee may also opt to pay one time service charges for 10 years, in advance at 6<br />

times <strong>of</strong> prevailing rate. After expiry <strong>of</strong> 10 financial years, a block <strong>of</strong> another 10<br />

years shall commence from 1st April, <strong>of</strong> 11th financial year and service charges for<br />

that block equivalent to six times the rate fixed at that time shall be paid before 31st<br />

July <strong>of</strong> the financial year and so on.<br />

(Inserted as per IDC decisions taken vide item 6 & 12 on 5.7.2000 & on 30.09.2000<br />

respectively)<br />

15(A) (iv). Service Charges shall be recovered in all Industrial Areas from the date <strong>of</strong><br />

declaration <strong>of</strong> the area as developed.<br />

15(A)(v). No Service Charges will be levied upon the allottees to whom plots have been<br />

allotted for the following purposes :<br />

(a) Industries Association - for construction <strong>of</strong> association building.<br />

(b) Power Companies (erstwhile RSEB)-For setting up power Grid Sub Station<br />

(GSS) <strong>of</strong> 220/132 KV & 33 KV.<br />

(c) PHED - For water supply scheme/arrangements in the area itself.<br />

(d) Director <strong>of</strong> Industries - For DIC building<br />

(e) Police Department - For Police Chowki<br />

(Inserted as per IDC decision taken vide item 10 & 10-a on 12.5.81item 8 on 31.5.88. )<br />

15(A) (vi) No service charges shall be levied upon industrial plot allottees in industrial areas<br />

including transferred industrial areas for the period unit remains closed and also no<br />

interest shall be levied on old outstanding service charges for the closure period. The<br />

closure period will be reconed from the date <strong>of</strong> disconnection <strong>of</strong> power supply/<br />

electric connection till the date <strong>of</strong> the reconnection. The allottee shall provide<br />

adequate pro<strong>of</strong> regarding disconnection <strong>of</strong> power supply from the concerned<br />

department and the benefit will begiven on the physical and record verification <strong>of</strong> the<br />

closure <strong>of</strong> the unit by the unit <strong>of</strong>fice.<br />

(Amended as per IDC decision vide item 8 <strong>of</strong> its meeting dt. 18.2.2011)