06.08.2013 Views

The Alaska Contractor - Summer 2008

The Alaska Contractor - Summer 2008

The Alaska Contractor - Summer 2008

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Coeur hopes to<br />

begin production at<br />

Kensington gold mine<br />

in 2009<br />

BY PATRICIA LILES<br />

With completed underground mine workings and surface<br />

processing facilities, the Kensington mine northeast<br />

of Juneau should be producing about 150,000<br />

ounces of gold annually, employing about 200 people in the<br />

year-round operation.<br />

But instead, the recently constructed underground hardrock<br />

mine and surface processing facilities sit idle, even after<br />

the mine’s developer, Idaho-based Coeur d’Alene Mines<br />

has spent some $270 million to build the new operation.<br />

Problem is – the mine’s planned operation for disposal of<br />

tailings, which is the rock left over after gold is extracted, has<br />

to be changed to a process that will not only meet regulatory<br />

approval, but will pass muster with environmental groups<br />

that protested the project’s waste storage plan.<br />

Managers at Coeur <strong>Alaska</strong> had planned to store the leftover<br />

rock in the Lower Slate Lake, a 23-acre alpine lake. That<br />

process was included in Kensington’s plan of operation that<br />

concluded in 2005 with the approval of federal and state regulatory<br />

permits and the start of construction in mid-2005.<br />

Environmental groups argued against the tailing disposal<br />

plan and appealed the permits issued by regulatory agencies,<br />

a conflict that ultimately resulted in the wetlands permit for<br />

the tailings disposal plan to be suspended by federal regulators.<br />

<strong>The</strong> previously approved plan was argued thorough a<br />

variety of court proceedings, concluding with a March 2007<br />

ruling by the Ninth Circuit Court of Appeals that vacated the<br />

permits associated with the tailing facility.<br />

Meanwhile, construction crews working for Coeur continued<br />

on the underground mine workings and the surface<br />

processing plant and other related facilities. That work was<br />

concluded in August 2007, according to Coeur.<br />

In January <strong>2008</strong>, Coeur submitted a modified plan of operation<br />

to the U.S. Forest Service, the lead regulatory agency

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!